Summary

PRBD202107461
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Repair/Replace
Not Required
Tenant fit up of an existing space in Mall of America, with demolition, new walls, new storefront, new washroom and new fixtures.
06/15/2021
07/23/2021
04/11/2022
10/13/2021

Locations

Permits

Permit Number: PRBD202107461

Building
Finaled
07/23/2021
04/11/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 8/18/2021 (10:00 - 12:00) 8/18/2021 (AM) 08/18/2021
Corrections:


Miscellaneous/Other
Comment Only
08/18/2021
Furred wall framing in sales, bathroom, and locker area. Dividing wall old sales to BOH. Approved

Framing Inspection Passed 8/26/2021 (8:00 - 10:00) 8/26/2021 (AM) 08/26/2021
Corrections:


Miscellaneous/Other
Comment Only
08/26/2021
Wall and ceiling framing approved, pending pictures of fire stops at the 2floor drains.

Fire Inspection Final Passed 10/6/2021 (8:00 - 10:00) 10/6/2021 (AM) 10/06/2021
Progress Inspection Passed 10/06/2021
Corrections:


Miscellaneous/Other
Comment Only
10/06/2021
Approved to stock, train, setup, and bring in merchandise. No opening at this time. Final inspection must be called in and scheduled, all trades inspections to be completed and work. Call for final when ready.

Building Final Inspection Partial Pass 10/6/2021 (8:00 - 10:00) 10/6/2021 (AM) 10/06/2021
Corrections:


Miscellaneous/Other
Comment Only
10/06/2021
Approved to stock, train, setup, and bring in merchandise. No opening at this time. Final inspection to be called in, and all trades inspections to be completed and space to be ready for final turnover. Call for when ready. No final or approval can be given at this time to open.

Building Final Inspection Passed 10/13/2021 (8:00 - 10:00) 10/13/2021 (AM) 10/13/2021
Corrections:


Miscellaneous/Other
Comment Only
10/13/2021
Final approved. Ok to open to public. Mall to install address numbers.