PRBD202109796
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 10/11/2021 (8:00 - 10:00) | 10/11/2021 (AM) | 10/11/2021 |
Corrections:
Miscellaneous/Other
Carried Forward
10/11/2021
1) Patch 2 columns with Cafco Blazeshield Handpatch. Leave open for inspection.
2) fire stop the 4 cast pipes and 1 copper pipe Through floor in bathroom and utility room. Leave open for inspection.
3) remove the wood backing in wall at storefront.
|
||||
Miscellaneous/Other
Comment Only
10/11/2021
Approved to cover walls only, leave open areas needed for inspection as noted in the outstanding comments. See outstanding comments for correction.
|
||||
Framing Inspection | Partial Pass | 10/19/2021 (8:00 - 10:00) | 10/19/2021 (AM) | 10/19/2021 |
Corrections:
Miscellaneous/Other
Resolved
10/19/2021
1) Patch 2 columns with Cafco Blazeshield Handpatch. Leave open for inspection.
2) fire stop the 4 cast pipes and 1 copper pipe Through floor in bathroom and utility room. Leave open for inspection.
3) remove the wood backing in wall at storefront.
|
||||
Miscellaneous/Other
Comment Only
10/19/2021
Viewed fire stops, patched fireproofing, storefront framing, and supports added to ceiling framing for the added soffits.
Access panels needed to be installed at ceiling.
No ceiling covering till mechanical, sprinkler, and electrical inspections are approved.
|
||||
Fire Inspection Final | Not Ready | 11/19/2021 (10:00 - 12:00) | 11/19/2021 (AM) | 11/19/2021 |
Building Final Inspection | Failed | 11/22/2021 (8:00 - 10:00) | 11/22/2021 (AM) | 11/22/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/22/2021
Not ready for final.
Complete fitting rooms and signage. Complete bathroom and call in all inspections for trades permits.
Reschedule this final when completed.
|
||||
Fire Inspection Final | Passed | 11/23/2021 (8:00 - 10:00) | 11/23/2021 (AM) | 11/23/2021 |
Building Final Inspection | Partial Pass | 11/23/2021 (10:00 - 12:00) | 11/23/2021 (AM) | 11/23/2021 |
Corrections:
Miscellaneous/Other
Outstanding
11/23/2021
1) Accessibility signage to fitting room and bathroom must have raised lettering and brail.
2) install smoke seal at rear exit door .
|
||||
Building Final Inspection | Passed | 12/3/2021 (8:00 - 10:00) | 12/3/2021 (AM) | 12/03/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/03/2021
Items corrected, final for this permit approved.
|