PRBD202109802
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 9/1/2021 (12:30 - 2:30) | 9/1/2021 (PM) | 09/01/2021 |
Fire Inspection Final | Not Ready | 11/15/2021 (8:00 - 10:00) | 11/15/2021 (AM) | 11/15/2021 |
Building Final Inspection | Passed w/ Conditions | 11/15/2021 (8:00 - 10:00) | 11/15/2021 (AM) | 11/15/2021 |
Need fire marshal final - for sprinkler rough in and sprinkler final with fire alarm. A. Building permit final - passed, but with conditions to final fire sprinkler and fire alarm. | ||||
Corrections:
Miscellaneous/Other
Outstanding
11/15/2021
Building final passed, but with conditions that fire marshal sprinkler and fire alarm get passed.
|
||||
Fire Inspection Final | Passed | 12/17/2021 |