PRBD202111102
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 12/1/2021 (8:00 - 10:00) | 12/1/2021 (AM) | 12/01/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/01/2021
Storefront soffit and ceiling tie in framing approved. Contractor to have electrical, hvac, and sprinkler inspections prior ro covering lids.
The wood framed storefront was demo’d out, the city will allow the fire treated wood framed curb to stay in place due to the finished floor with the waterproofing membrane being connected to it. Contractor proposed a stainless steel metal cap to go over top of the exposed wood curb to encapsulate the wood… the city will allow this.
|
||||
Building Final Inspection | Failed | 5/4/2022 (8:00 - 10:00) | 5/4/2022 (AM) | 05/04/2022 |
Corrections:
Miscellaneous/Other
Comment Only
05/04/2022
This was a progress inspection with regard to permit final and opening to public.
Corrections with electrical, and environmental health to be completed. Call for inspection when ready.
|
||||
Building Final Inspection | Passed w/ Conditions | 5/9/2022 (12:30 - 2:30) | 5/9/2022 (PM) | 05/09/2022 |
Corrections:
Miscellaneous/Other
Comment Only
05/09/2022
Final approved, pending environmental health final when all their corrections are completed.
|
||||
Fire Inspection Final | Passed | 5/9/2022 (12:30 - 2:30) | 5/9/2022 (PM) | 05/09/2022 |