Permit Application Status

PRBD202111166


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202111166
Building
Finaled
GKII NORTHLAND CENTER LLC
Alteration/Repair/Replace
Not Required
Tenant Improvement in an existing space.
08/23/2021
10/08/2021
05/14/2022
11/15/2021

Locations

Permits

Permit Number: PRBD202111166

Building
Finaled
10/08/2021
05/14/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 10/28/2021 (8:00 - 10:00) 10/28/2021 (AM) 10/28/2021
Corrections:


Miscellaneous/Other
Comment Only
10/28/2021
Framing - passed. A. Existing accessible sink and countertop. B. Existing mechanical. C. Adding one sprinkler head. Please call for a rough in (above ceiling) inspection from the fire marshal, after fire sprinkler work has been completed.

Fire Inspection Final Passed 11/12/2021 (10:00 - 12:00) 11/12/2021 (AM) 11/15/2021
Building Final Inspection Passed 11/15/2021 (12:30 - 2:30) 11/15/2021 (PM) 11/15/2021
Existing tenant space for new Attorneys office. All trade finals passed. Building final passed.