PRBD202111637
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Framing Inspection | Pending | |||
Framing Inspection | Partial Pass | 10/27/2021 (8:00 - 10:00) | 10/27/2021 (AM) | 10/27/2021 |
Corrections:
Miscellaneous/Other
Comment Only
10/27/2021
Phase1 wall framing in suite 300… approved
|
||||
Framing Inspection | Passed | 11/4/2021 (10:00 - 12:00) | 11/4/2021 (AM) | 11/04/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/04/2021
Wall framing for second floor phase 2… approved
|
||||
Progress Inspection | Passed | 12/3/2021 (10:00 - 12:00) | 12/3/2021 (AM) | 12/03/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/03/2021
Suites 300 and 200, above ceiling… approved
|
||||
Building Final Inspection | Partial Pass | 2/17/2022 (12:30 - 2:30) | 2/17/2022 (PM) | 02/17/2022 |
Corrections:
Miscellaneous/Other
Comment Only
02/17/2022
Phase 1 & 2 is approved for final and occupancy.
This permit will remain open for the renovation of phase 3 of this project.
|
||||
Fire Inspection Final | Partial Pass | 2/17/2022 (12:30 - 2:30) | 2/17/2022 (PM) | 02/18/2022 |
Framing Inspection | Partial Pass | 5/11/2022 (8:00 - 10:00) | 5/11/2022 (AM) | 05/11/2022 |
Corrections:
Miscellaneous/Other
Comment Only
05/11/2022
Phase 3, wall framing approved . Sprinkler work needed where heads are in wall, and electrical inspection also to be done prior to covering.
|
||||
Building Final Inspection | Passed | 7/13/2022 (12:30 - 2:30) | 7/13/2022 (PM) | 07/13/2022 |
Corrections:
Miscellaneous/Other
Comment Only
07/13/2022
Final for this scope of work and permit approved
|
||||
Fire Inspection Final | Passed | 7/13/2022 (12:30 - 2:30) | 7/13/2022 (PM) | 07/14/2022 |