PRBD202111709
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 11/4/2021 (8:00 - 10:00) | 11/4/2021 (AM) | 11/04/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/04/2021
Wall framing approved, contractor to provide photos of fire stops at floor penetrations.
Possible change in ceiling may require a separate bulkhead to be installed, inquire with inspector if this change happens.
|
||||
Progress Inspection | Passed w/ Conditions | 12/7/2021 (8:00 - 10:00) | 12/7/2021 (AM) | 12/07/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/07/2021
Above ceiling and ceiling framing approved… install access panel for fire damper located in bathroom.
|
||||
Fire Inspection Final | Passed | 12/16/2021 | ||
Building Final Inspection | Partial Pass | 12/16/2021 (8:00 - 10:00) | 12/16/2021 (AM) | 12/16/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/16/2021
Approved for stock and training once space is cleaned.
Call for final once all work and trades inspections are completed.
|
||||
Building Final Inspection | Passed | 12/20/2021 (8:00 - 10:00) | 12/20/2021 (AM) | 12/20/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/20/2021
Final for this permit approved, ok to open to public.
|