PRBD202112332
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Building Final Inspection | Pending | |||
| Fire Inspection Final | Pending | |||
| Lath Inspection | Pending | |||
| Insulation Inspection | Pending | |||
| Footing Inspection | Pending | 1/21/2022 (8:00 - 10:00) | ||
| 1/21/22 Contractor called to cancel the inspection today, 1/21/2022 due to cold weather. jms | ||||
| Footing Inspection | Not Ready | 1/25/2022 (10:00 - 12:00) | 1/25/2022 (AM) | 01/25/2022 |
| Footing Inspection | Not Ready | 1/26/2022 (10:00 - 12:00) | 1/26/2022 (AM) | 01/26/2022 |
| Footing Inspection | Partial Pass | 1/27/2022 (10:00 - 12:00) | 1/27/2022 (AM) | 01/27/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/27/2022
Foundation subcontractor failed to have inspections for phase 1 footings and poured walls. Special inspector (Braun) to perform additional crush tests to confirm proper cold weather installations for phase 1.
|
||||
| Footing Inspection | Passed | 2/3/2022 (10:00 - 12:00) | 2/3/2022 (AM) | 02/03/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/03/2022
Progress inspection of footings in phase 2 approved.
|
||||
| Footing Inspection | Passed | 2/4/2022 (10:00 - 12:00) | 2/4/2022 (AM) | 02/04/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/04/2022
Remaining footings in phase 2 approved.
|
||||
| Footing Inspection | Passed | 2/8/2022 (10:00 - 12:00) | 2/8/2022 (AM) | 02/08/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/08/2022
Remaining poured walls for main structure approved.
|
||||
| Footing Inspection | Passed | 2/9/2022 (12:30 - 2:30) | 2/9/2022 (PM) | 02/09/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/09/2022
Progress inspection of elevator pit underpinning approved.
|
||||
| Footing Inspection | Passed | 2/23/2022 (12:30 - 2:30) | 2/23/2022 (PM) | 02/23/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/23/2022
Four piers for canopy approved.
|
||||
| Framing Inspection | Passed | 4/12/2022 (10:00 - 12:00) | 4/12/2022 (AM) | 04/12/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/12/2022
Parapet framing approved.
|
||||
| Framing Inspection | Passed | 5/24/2022 (12:30 - 2:30) | 5/24/2022 (PM) | 05/24/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/24/2022
Wall and soffit framing at level 1… approved
|
||||