Summary

PRBD202113550
Building
Finaled
ROERS MN OPP ZONE FUND LLC
New
Not Required
New 146-Unit Market Rate Apartment - 5-Floors Wood-Frame over Precast Concrete Podium Level (Steel Stud-Frame) and 2-Levels Below-Grade Parking Amenities include Plaza Deck with Exterior Swimming Pool, Plaza Deck with Pickleball Court, and Common Area Roof Deck on top floor.
10/12/2021
04/05/2022
04/09/2024
10/12/2023

Locations

Permits

Permit Number: PRBD202113550

Building
Finaled
04/05/2022
04/09/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection Failed 5/2/2022 (10:00 - 12:00) 5/2/2022 (AM) 05/02/2022
Corrections:


Miscellaneous/Other
Carried Forward
05/02/2022
Viewed the first layer to the outside of the stair shaft. 1) gypsum used must be approved for exterior use when building is not weather tight. 2) fasteners used must be approved for use with the gypsum assembly used and what is called out on the plans. What is used from the panel shop is interior grade FireGuard X ToughRock, and is not to have any moisture contact. It is also fastened with Roofing nails and sunk into the board 1/3- almost 1/2 depth of the gypsum. No further covering to take place, contractor to get the proper materials and fasteners and redo these panels and any other rated panels used in shaft Construction.

Progress Inspection Partial Pass 5/11/2022 (2:30 - 3:30) 5/11/2022 (PM) 05/11/2022
Corrections:


Miscellaneous/Other
Resolved
05/11/2022
Viewed the first layer to the outside of the stair shaft. 1) gypsum used must be approved for exterior use when building is not weather tight. 2) fasteners used must be approved for use with the gypsum assembly used and what is called out on the plans. What is used from the panel shop is interior grade FireGuard X ToughRock, and is not to have any moisture contact. It is also fastened with Roofing nails and sunk into the board 1/3- almost 1/2 depth of the gypsum. No further covering to take place, contractor to get the proper materials and fasteners and redo these panels and any other rated panels used in shaft Construction.

Miscellaneous/Other
Comment Only
05/11/2022
Outside layer of gypsum at first floor south stair … approved Poly barrier at slab on grade in stair.. approved Gypsum has been changed out to be weather resistant while in the exposed building phase of construction , fasteners have also been changed to the approved fasteners as spec’d on plans.

Progress Inspection Partial Pass 5/17/2022 (8:00 - 10:00) 5/17/2022 (AM) 05/17/2022
Corrections:


Miscellaneous/Other
Comment Only
05/17/2022
Outer gypsum layer to south stair and shaft at 2nd level… approved

Progress Inspection Partial Pass 5/25/2022 (8:00 - 10:00) 5/25/2022 (AM) 05/25/2022
Corrections:


Miscellaneous/Other
Comment Only
05/25/2022
S.W. stair and shaft, third level …. First layer of outer gypsum approved

Progress Inspection Partial Pass 6/6/2022 (8:00 - 10:00) 6/6/2022 (AM) 06/06/2022
Corrections:


Miscellaneous/Other
Comment Only
06/06/2022
5th level SW stair outer layer of gypsum… approved

Progress Inspection Not Ready 6/13/2022 (10:00 - 12:00) 6/13/2022 (AM) 06/13/2022
Corrections:


Miscellaneous/Other
Comment Only
06/13/2022
Inspection was canceled and will be rescheduled when ready for inspection.

Progress Inspection Partial Pass 06/15/2022
Corrections:


Miscellaneous/Other
Comment Only
06/15/2022
SW stairwell and shaft of 6th floor… first outer layer gypsum board approved.

Progress Inspection Partial Pass 7/1/2022 (8:00 - 10:00) 7/1/2022 (AM) 07/01/2022
Corrections:


Miscellaneous/Other
Comment Only
07/01/2022
Center elevator shaft and mechanical shaft at phase 2, level 2… outer layer of gypsum approved, pending the repair to broken gypsum board and added fasteners to layer. Verbal corrections, and job superintendent to monitor corrections.

Progress Inspection Partial Pass 7/8/2022 (8:00 - 10:00) 7/8/2022 (AM) 07/08/2022
Corrections:


Miscellaneous/Other
Comment Only
07/08/2022
Outer gypsum layer to north 2nd floor stair shaft… approved

Progress Inspection Partial Pass 7/11/2022 (10:00 - 12:00) 7/11/2022 (AM) 07/11/2022
Corrections:


Miscellaneous/Other
Comment Only
07/11/2022
Progress inspection of floor trusses and shear walls for 2nd floor zone 1. Shear wall “J” are approved, pending fasteners being added in the locations marked at walls. Trusses appear to be in proper bearing .

Progress Inspection Partial Pass 7/13/2022 (10:00 - 12:00) 7/13/2022 (AM) 07/13/2022
Corrections:


Miscellaneous/Other
Comment Only
07/13/2022
3rd floor zone 1, shear walls “J” … approved Roof washer dabits and the bracing at underside of roof installed… need to have pull test done prior to use… Partial approval of install, pending pull test.

Progress Inspection Partial Pass 7/15/2022 (10:00 - 12:00) 7/15/2022 (AM) 07/15/2022
Corrections:


Miscellaneous/Other
Comment Only
07/15/2022
3rd floor stair shaft, outer layer of gypsum… approved, pending the 2outer panels be screwed to match the fastening pattern of the wall assembly. Roofing nails cannot be used in this application.

Progress Inspection Partial Pass 7/28/2022 (12:30 - 2:30) 7/28/2022 (PM) 07/28/2022
Corrections:


Miscellaneous/Other
Comment Only
07/28/2022
Zone 2 4th floor, first layer of gypsum at all shafts, approved

Progress Inspection Partial Pass 8/10/2022 (12:30 - 2:30) 8/10/2022 (PM) 08/10/2022
Corrections:


Miscellaneous/Other
Comment Only
08/10/2022
1st outer layer of gypsum board to the shafts on 5th floor, zone 2 ... approved

Progress Inspection Partial Pass 8/18/2022 (12:30 - 2:30) 8/18/2022 (PM) 08/18/2022
Corrections:


Miscellaneous/Other
Comment Only
08/18/2022
Zone 2, 5th floor … outer first layer of gypsum to all shafts approved.

Progress Inspection Not Ready 9/15/2022 (12:30 - 2:30) 9/15/2022 (PM) 09/15/2022
Corrections:


Miscellaneous/Other
Comment Only
09/15/2022
Mock inspection with the job superintendent and apprentice to go over what needs to be inspected and what we look for.

Progress Inspection Partial Pass 9/20/2022 (12:30 - 2:30) 9/20/2022 (PM) 09/20/2022
Corrections:


Miscellaneous/Other
Comment Only
09/20/2022
Zone one, floors 4,5,&,6… verified building tension rod system and installation in units. Contractor has 3 units locations that rods need to be completed with correct installation.

Progress Inspection Not Ready 9/22/2022 (12:30 - 2:30) 9/22/2022 (PM) 09/22/2022
Corrections:


Miscellaneous/Other
Carried Forward
09/22/2022
Started framing and fire stop inspection on zone 1, 6th floor. Need information on the bearing blocks at the I-Joists as to where it is needed per the design of the building and the loads. The straps that run through to the parapet on roof are not carrying the capacity that they are designed for, due to the nails either not going into the stud framing, or the stud framing has also been split to the point that the nails really aren’t doing any good. The engineer has to access this issue and direct accordingly. Inspection was halted after going through the units and finding some of the same situations of bearing for I-Joists in multiple units. Went to 3rd floor to continue with hold downs of the threaded rod assembly. The assemblies are still not completed in so much as the washers need to be tightened down with the nut and 1/2-1/3 turn tension needs to be completed. The bearing blocks also need to be installed within the floor cavity on each side of the threaded rods, this applies to floors 2-5. A recheck of the floors 4&5 is needed for the bearing blocks. Inspection was halted at this time for the contractor to have carpenter go through and complete these installations per the design.

Framing Inspection Partial Pass 9/26/2022 (10:00 - 12:00) 9/26/2022 (AM) 09/26/2022
Corrections:


Miscellaneous/Other
Comment Only
09/26/2022
zone 1, 6th floor unit framing and fire stops… approved

Insulation Inspection Passed 9/30/2022 (8:00 - 10:00) 9/30/2022 (AM) 09/30/2022
Corrections:


Miscellaneous/Other
Comment Only
09/30/2022
6th floor zone 1 unit insulation and poly… approved

Framing Inspection Partial Pass 9/30/2022 (Morning) 9/30/2022 (AM) 09/30/2022
Corrections:


Miscellaneous/Other
Comment Only
09/30/2022
5th floor zone 1 framing and fire stops, approved. See outstanding comments for correction.

Miscellaneous/Other
Outstanding
09/30/2022
Unit 501 needs a floor truss fix due to the metal cleat being removed. Truss is marked at wall for location.

Insulation Inspection Partial Pass 10/6/2022 (10:00 - 12:00) 10/6/2022 (AM) 10/06/2022
Corrections:


Miscellaneous/Other
Comment Only
10/06/2022
Zone 1, Sixth floor first layer of gypsum at rated ceilings/roof. Approved

Progress Inspection Not Ready 10/7/2022 (8:00 - 10:00) 10/7/2022 (AM) 10/07/2022
Corrections:


Miscellaneous/Other
Comment Only
10/07/2022
Inspection canceled, not ready.

Progress Inspection Partial Pass 10/10/2022 (8:00 - 10:00) 10/10/2022 (AM) 10/10/2022
Corrections:


Miscellaneous/Other
Comment Only
10/10/2022
Zone one…, fifth floor units insulation and poly approved. Fourth floor framing & fire stops of units in zone one, approved

Progress Inspection Not Ready 10/13/2022 (8:00 - 10:00) 10/13/2022 (AM) 10/13/2022
Corrections:


Miscellaneous/Other
Comment Only
10/13/2022
Fire stops to be completed for this 3rd floor inspection. Not ready at this time.

Progress Inspection Partial Pass 10/14/2022 (8:00 - 10:00) 10/14/2022 (AM) 10/14/2022
Corrections:


Miscellaneous/Other
Carried Forward
10/14/2022
Hallway needs fire collars at the rain leader piping location is marked on pipe. Wires Behring the stack of gypsum board to also be fire caulked.

Miscellaneous/Other
Comment Only
10/14/2022
Zone one, third floor unit framing and fire stops…. Approved

Insulation Inspection Partial Pass 10/17/2022 (10:00 - 12:00) 10/17/2022 (AM) 10/17/2022
Corrections:


Miscellaneous/Other
Comment Only
10/17/2022
4th floor zone one units insulation/poly… approved

Progress Inspection Not Ready 10/18/2022 (8:00 - 10:00) 10/18/2022 (AM) 10/18/2022
Corrections:


Miscellaneous/Other
Comment Only
10/18/2022
Inspection canceled, not ready

Progress Inspection Partial Pass 10/19/2022 (8:00 - 10:00) 10/19/2022 (AM) 10/19/2022
Corrections:


Miscellaneous/Other
Comment Only
10/19/2022
First floor zone 1, mock up unit framing and fire stops… approved. 4th floor remaining shear walls installed, approved and pending engineer approval where walls do not extend as designed with the wood shear, but gypsum is installed for remainder of wall.

Progress Inspection Partial Pass 10/21/2022 (8:00 - 10:00) 10/21/2022 (AM) 10/21/2022
Corrections:


Miscellaneous/Other
Carried Forward
10/21/2022
Hallway needs fire collars at the rain leader piping location is marked on pipe. Wires Behring the stack of gypsum board to also be fire caulked.

Miscellaneous/Other
Comment Only
10/21/2022
Mock unit105 insulation and poly approved. No covering of unit at this time until water piping has been insulated and inspected, and fire stops of through floor piping has been verified for the assembly being used.

Insulation Inspection Partial Pass 10/26/2022 (7:00 - 8:00) 10/26/2022 (AM) 10/26/2022
Corrections:


Miscellaneous/Other
Comment Only
10/26/2022
3rd floor units exterior wall insulation/poly… approved

Framing Inspection Partial Pass 10/27/2022 (2:30 - 3:30) 10/27/2022 (PM) 10/27/2022
Corrections:


Miscellaneous/Other
Comment Only
10/27/2022
Stoop footings along north and west side approved for concrete placement. 3rd floor zone 1 units and hallway framing and fire stops approved, pending the installation of 2 anchor bolts and fix to stair shaft wall. Reinspection of the fixes to be verified by inspection.

Progress Inspection Partial Pass 11/1/2022 (8:00 - 10:00) 11/1/2022 (AM) 11/01/2022
10/20/22 Inspection cancelled for today. jms
Corrections:


Miscellaneous/Other
Comment Only
11/01/2022
Viewed the corrections that were listed to units at last inspection, and marked at units… approved.

Insulation Inspection Partial Pass 11/3/2022 (12:30 - 2:30) 11/3/2022 (PM) 11/03/2022
Corrections:


Miscellaneous/Other
Comment Only
11/03/2022
Phase 1 level 2 unit insulation/poly at exterior walls… approved Stairwell framing from level 4 to roof… approved.

Progress Inspection Partial Pass 11/4/2022 (8:00 - 10:00) 11/4/2022 (AM) 11/04/2022
Corrections:


Miscellaneous/Other
Carried Forward
11/04/2022
Shear walls looked at on phase 1, 5th and 6th floors. Corrections with the screw pattern for shear walls given to contractor and to be verified at next inspection.

Progress Inspection Partial Pass 11/8/2022 (8:00 - 10:00) 11/8/2022 (AM) 11/08/2022
Corrections:


Miscellaneous/Other
Resolved
11/08/2022
Shear walls looked at on phase 1, 5th and 6th floors. Corrections with the screw pattern for shear walls given to contractor and to be verified at next inspection.

Miscellaneous/Other
Comment Only
11/08/2022
Phase 1…. Stairway viewed from level 2 to 6th floor, framing approved. First layer of gypsum at levels 4-6 approved with verbal corrections. Shear walls on 5&6 , screw patterns corrected… approved

Progress Inspection Partial Pass 11/9/2022 (8:00 - 10:00) 11/9/2022 (AM) 11/09/2022
Corrections:


Miscellaneous/Other
Comment Only
11/09/2022
Base 2 sixth floor hold downs and parapet strapping has been viewed…. Approved. Ok to foam the outside rims.

Progress Inspection Failed 11/15/2022 (8:00 - 10:00) 11/15/2022 (AM) 11/15/2022
Corrections:


Miscellaneous/Other
Resolved
11/15/2022
Hallway needs fire collars at the rain leader piping location is marked on pipe. Wires Behring the stack of gypsum board to also be fire caulked.

Miscellaneous/Other
Outstanding
11/15/2022
Phase 1 stairwell from level 1-4 first layer of gypsum needs corrections with corner gaps and gaps between sheets. Large gaps cannot be used in rated assemblies. Contractor needs to follow the assembly requirements. Mechanical shaft interior gypsum first layer at 6th floor approved with correction of the pre rock layer to be fixed with the length of sheet and corners to be tight.

Progress Inspection Partial Pass 11/17/2022 (10:00 - 12:00) 11/17/2022 (AM) 11/17/2022
Corrections:


Miscellaneous/Other
Comment Only
11/17/2022
Miscellaneous gypsum shear walls in zone 1 , floors 2-4. Center Elevator… framing of floors 2-6… approved

Framing Inspection Partial Pass 11/21/2022 (12:30 - 2:30) 11/21/2022 (PM) 11/21/2022
Corrections:


Miscellaneous/Other
Comment Only
11/21/2022
Zone 2, 6th floor units marked at door entry and hallway and trash room/shaft… framing/fire stops… approved

Insulation Inspection Partial Pass 11/28/2022 (8:00 - 10:00) 11/28/2022 (AM) 11/28/2022
Corrections:


Miscellaneous/Other
Comment Only
11/28/2022
Zone 2, 6th floor insulation at marked units (that were already approved with framing)… approved

Framing Inspection Partial Pass 11/29/2022 (12:30 - 2:30) 11/29/2022 (PM) 11/29/2022
Corrections:


Miscellaneous/Other
Comment Only
11/29/2022
Zone 2, 5th floor…. Units marked signed off at door entry are approved for framing and fire stops. Hallway is also approved, pending the hanger fix at end of hallway. Reinspection of remaining units is needed, no insulation to be done where units are not signed off.

Framing Inspection Partial Pass 12/1/2022 (2:30 - 3:30) 12/1/2022 (PM) 12/01/2022
Corrections:


Miscellaneous/Other
Comment Only
12/01/2022
Zone 2, remaining units for framing and fire stops… approved Insulation and poly to units… Approved Zone 1 membrane fire stops at units on floors 5&6… approved

Framing Inspection Partial Pass 12/2/2022 (8:00 - 10:00) 12/2/2022 (AM) 12/02/2022
Corrections:


Miscellaneous/Other
Comment Only
12/02/2022
Zone 1, floors 2-4… one side membrane fire stops in units approved

Framing Inspection Partial Pass 12/8/2022 (2:30 - 3:30) 12/8/2022 (PM) 12/08/2022
Corrections:


Miscellaneous/Other
Comment Only
12/08/2022
Zone 2. 4th floor…. Units marked at door are approved for framing and fire stops. 5th floor remaining unit approved. 6th floor first layer of gypsum at elevator shaft… approved.

Progress Inspection Partial Pass 12/9/2022 (8:00 - 10:00) 12/9/2022 (AM) 12/09/2022
Corrections:


Miscellaneous/Other
Resolved
12/09/2022
Started framing and fire stop inspection on zone 1, 6th floor. Need information on the bearing blocks at the I-Joists as to where it is needed per the design of the building and the loads. The straps that run through to the parapet on roof are not carrying the capacity that they are designed for, due to the nails either not going into the stud framing, or the stud framing has also been split to the point that the nails really aren’t doing any good. The engineer has to access this issue and direct accordingly. Inspection was halted after going through the units and finding some of the same situations of bearing for I-Joists in multiple units. Went to 3rd floor to continue with hold downs of the threaded rod assembly. The assemblies are still not completed in so much as the washers need to be tightened down with the nut and 1/2-1/3 turn tension needs to be completed. The bearing blocks also need to be installed within the floor cavity on each side of the threaded rods, this applies to floors 2-5. A recheck of the floors 4&5 is needed for the bearing blocks. Inspection was halted at this time for the contractor to have carpenter go through and complete these installations per the design.

Miscellaneous/Other
Comment Only
12/09/2022
Zone 2, 4th floor all areas “EXCLUDING unit #414” are approved for framing and fire stops.

Insulation Inspection Partial Pass 12/13/2022 (12:30 - 2:30) 12/13/2022 (PM) 12/13/2022
Corrections:


Miscellaneous/Other
Outstanding
12/13/2022
Reinspection of dead space in units 423&523 needed when ready for reinspection. Do not cover the wall which allows access to this space.

Miscellaneous/Other
Comment Only
12/13/2022
Insulation approved in units 526,525,524,422,421,419,416,415,414,413,412… Framing and fire stops approved in North Stair floors 3-6.

Progress Inspection Partial Pass 12/14/2022 (8:00 - 10:00) 12/14/2022 (AM) 12/14/2022
Corrections:


Miscellaneous/Other
Comment Only
12/14/2022
Sky lounge/bath at 6th floor, framing and fire stops… approved Remaining 4 units of insulation at zone 2, 4th floor… approved Corrections in Dead space of unit at 5th floor… approved

Progress Inspection Partial Pass 12/15/2022 (12:30 - 2:30) 12/15/2022 (PM) 12/15/2022
Corrections:


Miscellaneous/Other
Comment Only
12/15/2022
Unit 612 framing and fire stops… approved Units 614 & 414 framing and fire stops approved, pending the installation of the hold downs at unit wall next to corridor wall. Verification of installation required prior to covering walls. Contractor to check this set of 14 stack units and make sure all the hold downs are in place as required.

Framing Inspection Partial Pass 12/16/2022 (8:00 - 10:00) 12/16/2022 (AM) 12/16/2022
Corrections:


Miscellaneous/Other
Comment Only
12/16/2022
Framing and fire stops of storage and elevator lobbies on 5th and 6th floor… approved Units 512&514 framing and fire stops…. Approved Framing and fire stops of Units only in zone 2, 3rd floor … units approved to insulate are , 313 to 326. Reinspection is needed for unit 312, and hallway and elevator, storage… Reinspection needed at dead space in unit 323.

Progress Inspection Partial Pass 12/20/2022 (12:30 - 2:30) 12/20/2022 (PM) 12/20/2022
Corrections:


Miscellaneous/Other
Comment Only
12/20/2022
Zone 2. unit 312 and hallway with elevator rooms and lobbies, and mechanical room… framing and fire stops approved. Insulation/at exterior walls in units 612,614,512,& 514… approved. Second layer of gypsum at 6th floor elevator shaft… approved

Progress Inspection Partial Pass 12/22/2022 (8:00 - 10:00) 12/22/2022 (AM) 12/22/2022
Corrections:


Miscellaneous/Other
Comment Only
12/22/2022
Dead space in units 423&523…. Approved Mechanical ducting and soffits in unit 613…. Approved First layer of gypsum in elevator shaft of 5th floor… approved

Progress Inspection Partial Pass 1/3/2023 (8:00 - 10:00) 1/3/2023 (AM) 01/03/2023
Corrections:


Miscellaneous/Other
Comment Only
01/03/2023
Zone 1 mechanical shaft floors 2-6, second layer of gypsum approved. Zone 2 second layer of gypsum at elevator… approved. Zone 2 third floor unit insulation at exterior walls…. Approved.

Progress Inspection Not Ready 1/4/2023 (8:00 - 10:00) 1/4/2023 (AM) 01/04/2023
Corrections:


Miscellaneous/Other
Comment Only
01/04/2023
Inspection canceled

Progress Inspection Partial Pass 1/5/2023 (8:00 - 10:00) 1/5/2023 (AM) 01/05/2023
Corrections:


Miscellaneous/Other
Comment Only
01/05/2023
Zone 2, 2nd level framing and fire stops… approved 2nd level insulation at units and all exterior walls… approved Stairwell gypsum first layer at floors 4-6… approved

Progress Inspection Partial Pass 1/10/2023 (8:00 - 10:00) 1/10/2023 (AM) 01/10/2023
Corrections:


Miscellaneous/Other
Carried Forward
01/10/2023
Elevator gypsum… first layer on floor 2&3, second layer on 4th…. Approved. North stair.. second layer on 5th& 6th, first layer on 4th… approved. First floor center mechanical shaft… corrections marked at shaft, contractor/installer to correct items. Unit 323… gypsum to be fastened off at wall in dead space, gypsum to be fully enclosed around the rain leader piping for the fire collars to be compliant with the collars installation.

Progress Inspection Partial Pass 1/11/2023 (8:00 - 10:00) 1/11/2023 (AM) 01/11/2023
Corrections:


Miscellaneous/Other
Comment Only
01/11/2023
Zone 2 2nd floor shear walls… approved

Progress Inspection Partial Pass 1/13/2023 (10:00 - 12:00) 1/13/2023 (AM) 01/13/2023
Corrections:


Miscellaneous/Other
Carried Forward
01/13/2023
Elevator gypsum… first layer on floor 2&3, second layer on 4th…. Approved. North stair.. second layer on 5th& 6th, first layer on 4th… approved. First floor center mechanical shaft… corrections marked at shaft, contractor/installer to correct items. Unit 323… gypsum to be fastened off at wall in dead space, gypsum to be fully enclosed around the rain leader piping for the fire collars to be compliant with the collars installation.

Miscellaneous/Other
Comment Only
01/13/2023
2nd layer of gypsum to elevator, floors 3-6… approved

Progress Inspection Partial Pass 1/17/2023 (8:00 - 10:00) 1/17/2023 (AM) 01/17/2023
Corrections:


Miscellaneous/Other
Comment Only
01/17/2023
Membrane fire stops on floors 4-6 zone 2… approved pending gas lines to be fire stopped and verified.

Progress Inspection Partial Pass 1/19/2023 (12:30 - 2:30) 1/19/2023 (PM) 01/19/2023
Corrections:


Miscellaneous/Other
Resolved
01/19/2023
Elevator gypsum… first layer on floor 2&3, second layer on 4th…. Approved. North stair.. second layer on 5th& 6th, first layer on 4th… approved. First floor center mechanical shaft… corrections marked at shaft, contractor/installer to correct items. Unit 323… gypsum to be fastened off at wall in dead space, gypsum to be fully enclosed around the rain leader piping for the fire collars to be compliant with the collars installation.

Miscellaneous/Other
Comment Only
01/19/2023
North end mechanical shaft first layer of gypsum approved. Insulation and poly at center mechanical shaft above roof approved.

Progress Inspection Not Ready 1/20/2023 (Afternoon) 1/20/2023 (PM) 01/20/2023
Contractor called to cancel today's inspection. jms [jsmidt @ 01/20/2023 11:57 AM] Texted Jon
Corrections:


Miscellaneous/Other
Comment Only
01/20/2023
Not ready for inspection, this inspection was canceled by contractor.

Progress Inspection Partial Pass 1/24/2023 (10:00 - 12:00) 1/24/2023 (AM) 01/24/2023
Corrections:


Miscellaneous/Other
Comment Only
01/24/2023
Gypsum layers at 2nd floor of elevator shaft… approved

Progress Inspection Partial Pass 1/25/2023 (12:30 - 2:30) 1/25/2023 (PM) 01/25/2023
Corrections:


Miscellaneous/Other
Comment Only
01/25/2023
North mechanical shaft floors 2-6 first layer of gypsum… approved

Progress Inspection Partial Pass 1/30/2023 (8:00 - 10:00) 1/30/2023 (AM) 01/30/2023
Corrections:


Miscellaneous/Other
Comment Only
01/30/2023
Second layer of gypsum at trash shaft, floors 2-6…. Approved

Progress Inspection Partial Pass 1/31/2023 (12:30 - 2:30) 1/31/2023 (PM) 01/31/2023
Corrections:


Miscellaneous/Other
Carried Forward
01/31/2023
Approved to insulate only the units from the south end of building to units 108&109 on first floor. Reinspection of the all units is needed to verify fire stops at walls and precast. The 3 foot soffit walls hanging from precast need to have a second screw installed at each of the upper framing members

Progress Inspection Partial Pass 2/1/2023 (8:00 - 10:00) 2/1/2023 (AM) 02/01/2023
Corrections:


Miscellaneous/Other
Comment Only
02/01/2023
Exterior insulation/poly for 5 units as marked in the entry door inspection sign off card… approved

Progress Inspection Partial Pass 2/3/2023 (10:00 - 12:00) 2/3/2023 (AM) 02/03/2023
Corrections:


Miscellaneous/Other
Comment Only
02/03/2023
Units and hallway from unit 101-110 approved for framing and fire stops. 1sr floor trash shaft 2 layers of gypsum… approved Note…. Framing at north stair at the angled walls to be corrected to what was approved on the city approved plans.

Progress Inspection Not Ready 2/6/2023 (8:00 - 10:00) 2/6/2023 (AM) 02/06/2023
Corrections:


Miscellaneous/Other
Comment Only
02/06/2023
Contractor canceled inspection, not ready.

Progress Inspection Partial Pass 2/8/2023 (8:00 - 10:00) 2/8/2023 (AM) 02/08/2023
Corrections:


Miscellaneous/Other
Carried Forward
02/08/2023
Fire stop detail needed for the wiring bundle located at each side corridor wall in second floor above the drop ceiling grid… fire stop to be installed and inspected, leave open for inspection.

Miscellaneous/Other
Comment Only
02/08/2023
2 more units of framing and fire stops at first floor… approved. Exterior wall insulation from units 100 to 110… approved See outstanding comments for correction and inspection.

Progress Inspection Partial Pass 2/9/2023 (10:00 - 12:00) 2/9/2023 (AM) 02/09/2023
Corrections:


Miscellaneous/Other
Comment Only
02/09/2023
Zone 2 2nd and 3rd floor membrane fire stops at units approved. Insulation at unit 111 approved

Progress Inspection Failed 2/22/2023 (12:30 - 2:30) 2/22/2023 (PM) 02/22/2023
Corrections:


Miscellaneous/Other
Resolved
02/22/2023
Approved to insulate only the units from the south end of building to units 108&109 on first floor. Reinspection of the all units is needed to verify fire stops at walls and precast. The 3 foot soffit walls hanging from precast need to have a second screw installed at each of the upper framing members

Miscellaneous/Other
Comment Only
02/22/2023
Progress inspection and consultation of north stairway 2hr wall and piping being run through stairway that does not serve stairway. Design professional needs to address these issues and submit alternate fix’s for approval with inspector.

Progress Inspection Partial Pass 2/28/2023 (10:00 - 12:00) 2/28/2023 (AM) 02/28/2023
Corrections:


Miscellaneous/Other
Comment Only
02/28/2023
Last 5 units to the north end of first level , exterior walls only are approved to be insulated and poly covered.

Progress Inspection Passed w/ Conditions 3/3/2023 (8:00 - 10:00) 3/3/2023 (AM) 03/03/2023
Corrections:


Miscellaneous/Other
Comment Only
03/03/2023
Units 113-117, framing and fire stops approved…. Fan coil piping in unit to be fire stopped, contractor to verify. Firestops at electrical runs in wall on floors 2,3,&4 approved, pending fire stop at open cored hole at bottom plate…. Contractor to also verify that and the wall patching of relocated duct opening.

Framing Inspection Partial Pass 3/9/2023 (8:00 - 10:00) 3/9/2023 (AM) 03/09/2023
Corrections:


Miscellaneous/Other
Comment Only
03/09/2023
Framing at first floor exterior walls of common areas, approved and ok to insulate.

Progress Inspection Not Ready 3/13/2023 (8:00 - 10:00) 3/13/2023 (AM) 03/13/2023
Corrections:


Miscellaneous/Other
Comment Only
03/13/2023
Not ready for inspection.

Progress Inspection Partial Pass 3/16/2023 (12:30 - 2:30) 3/16/2023 (PM) 03/16/2023
Timeframe overlapping, set in the 12:30-2:30 window. VM 3/13/23
Corrections:


Miscellaneous/Other
Carried Forward
03/16/2023
Fire stop detail needed for the wiring bundle located at each side corridor wall in second floor above the drop ceiling grid… fire stop to be installed and inspected, leave open for inspection.

Miscellaneous/Other
Carried Forward
03/16/2023
First floor common areas…. Framing viewed and is approved. Firestops need to be completed in 3hr rated floor and at podium, and unit wall separation. Will recheck at next inspection.

Progress Inspection Not Ready 3/17/2023 (8:00 - 10:00) 3/17/2023 (AM) 03/17/2023
Corrections:


Miscellaneous/Other
Comment Only
03/17/2023
Contractor canceled inspection, and rescheduled for 3/20

Progress Inspection Partial Pass 3/20/2023 (10:00 - 12:00) 3/20/2023 (AM) 03/20/2023
Corrections:


Miscellaneous/Other
Comment Only
03/20/2023
Membrane fire stops at first floor units on north end. Common area of first level framing and partial in wall fire stops. Approved to cover walls only. Note… 2hr stair wall at north stair to still be corrected, no covering of this area so work can be done to fix the issue and inspect.wall.

Progress Inspection Failed 3/27/2023 (8:00 - 10:00) 3/27/2023 (AM) 03/27/2023
Corrections:


Miscellaneous/Other
Outstanding
03/27/2023
5th and 6th floor shaft walls at elevator fronts…. Walls need to be fixed and fire stopped at penetrations of electrical. The assembly in place has many panels that need to be properly fastened, cuts that should not be in place per the listing of assembly, framing that leaves large voids between the wall and door jamb. These walls need to be redone and reinspected.

Progress Inspection Partial Pass 3/29/2023 (8:00 - 10:00) 3/29/2023 (AM) 03/29/2023
Corrections:


Miscellaneous/Other
Comment Only
03/29/2023
Shaft wall front wall at elevator fronts on floors 3,4,5,&6…. Corrections given on 5&6, those to be reinspected. Floors 3&4 can be first layered with gypsum.

Progress Inspection Partial Pass 3/30/2023 (10:00 - 12:00) 3/30/2023 (AM) 03/30/2023
Corrections:


Miscellaneous/Other
Comment Only
03/30/2023
Elevator front shaft wall on floors 4,5,&6 have been fire stopeed and corrected as needed to comply with the shaft wall requirements. Approved to cover this wall. South mechanical shaft at 6th floor tip in wall is a core board assembly and fire stopped at the through joints. Approved to cover this outside wall layer.

Progress Inspection Not Ready 4/6/2023 (10:00 - 12:00) 4/6/2023 (AM) 04/06/2023
Corrections:


Miscellaneous/Other
Comment Only
04/06/2023
Front walls at the elevators need to be redone to the assembly provided by the elevator company. Unable to view the wall at the inside of the shaft since access was not possible at the time of inspection of these walls. The problem was found when the elevator installer saw the inside of the shaft wall and the elevator installer needs to do some adjustment with the rails to allow the shaft wall to be built as per the assembly they provided. The walls will be taken apart and redone after the elevator installer does the corrections, inspection of the rebuilt walls will be done as they are reinstalled.

Housewrap Inspection Passed 04/10/2023
Corrections:


Miscellaneous/Other
Comment Only
04/10/2023
All housewrap has been inspected and approved at different intervals of time as the job progressed.

Progress Inspection Partial Pass 10/11/2022 (8:00 - 10:00) 04/10/2023
Per caller (Mike), cancelling 10/11 inspection. [Hernandez Martinez\, Veronica @ 10/10/2022 3:43 PM]
Corrections:


Miscellaneous/Other
Comment Only
04/10/2023
Fire stops viewed in common ares of first floor above ceiling. Ceiling edges along the rated walls that butt up to the residential units are to remain open for further inspection when those areas are ready for inspection. Viewed the mechanical shaft tip in walls at the 3 mechanical shafts on each floor. Approved to add the 2 layers of gypsum and leave open for inspection.

Progress Inspection Partial Pass 4/11/2023 (12:30 - 2:30) 4/11/2023 (PM) 04/11/2023
Corrections:


Miscellaneous/Other
Comment Only
04/11/2023
Hallway mechanical shafts (3 per floor) at floors 2-6… outer 2 layers of gypsum, and double gypsum wraps and fire caulking used at voids…. Approved

Progress Inspection Passed w/ Conditions 4/14/2023 (10:00 - 12:00) 4/14/2023 (AM) 04/14/2023
Corrections:


Miscellaneous/Other
Comment Only
04/14/2023
Above ceiling fire stops of common area bathrooms and hallway at the rated wall, and firestops in fitness room at rate wall. Note… walls need to be perimeter fire stopped, contractor to verify this completion before covering.

Progress Inspection Partial Pass 04/17/2023
Corrections:


Miscellaneous/Other
Comment Only
04/17/2023
Partial 2 hr shaft wall at First floor of north stairway 3 hour seperation shaft lids in north and south stairwells of first level, (installation of these are required due to items run in stairwell that do not serve stairwell.). Partial approval of these assemblies, conditional upon reinspection of the layers to be installed at the shaft lids and remaining wall to be built and tied into the 2hr shaft wall at stairway.

Progress Inspection Partial Pass 4/18/2023 (12:30 - 2:30) 4/18/2023 (PM) 04/18/2023
Corrections:


Miscellaneous/Other
Resolved
04/18/2023
Fire stop detail needed for the wiring bundle located at each side corridor wall in second floor above the drop ceiling grid… fire stop to be installed and inspected, leave open for inspection.

Miscellaneous/Other
Resolved
04/18/2023
First floor common areas…. Framing viewed and is approved. Firestops need to be completed in 3hr rated floor and at podium, and unit wall separation. Will recheck at next inspection.

Miscellaneous/Other
Comment Only
04/18/2023
Elevator front shaft wall, floors 1-5 are installed per the UL assembly provided within the elevator installation guide. Floors 2&5 electrical room fire stops… approved per the detail provided by firestop mfg. fitness room soffit framing and firestops within … approved Above ceilingand fire stops in bathrooms on first level… approved

Progress Inspection Passed 04/19/2023
Corrections:


Miscellaneous/Other
Comment Only
04/19/2023
Viewed the elevator front walls on floors 2-5, first layer of 5/8”gypsum approved. Ok to second layer theses walls.

Progress Inspection Partial Pass 4/20/2023 (8:00 - 10:00) 4/20/2023 (AM) 04/20/2023
Corrections:


Miscellaneous/Other
Comment Only
04/20/2023
1st and second layers on elevator front shaft wall for floors 2-6 approved, pending inspection of the fire caulking at 2&3, and installing additional 2 layers per assembly at the 6th floor wall.

Progress Inspection Partial Pass 4/21/2023 (10:00 - 12:00) 4/21/2023 (AM) 04/21/2023
Corrections:


Miscellaneous/Other
Comment Only
04/21/2023
Rode elevator car top to view the inside of the shaft. The sealing of shaft is as good as can be done and meets the intent of the code for the shaft requirements.

Progress Inspection Partial Pass 4/25/2023 (10:00 - 12:00) 4/25/2023 (AM) 04/25/2023
Corrections:


Miscellaneous/Other
Comment Only
04/25/2023
Elevator front walls at floors 2&3 are firestopped ... ok to complete fur wall. Elevator front wall at level 6, has gypsum installed with 2 layers to cover the service box as per the design...ok to complete fur wall. 3 added layers of gypsum baord to the furred ceiling assembly in south stair... approved. See outstanding comments for corrections to be viewed at next inspection.

Miscellaneous/Other
Carried Forward
04/25/2023
North stair 2 hr wall section needs to have studs added for the full height of wall at each end of that wall section and it needs to be tied into the top and buttom framing tracks.

Progress Inspection Partial Pass 4/26/2023 (10:00 - 12:00) 4/26/2023 (AM) 04/26/2023
Corrections:


Miscellaneous/Other
Comment Only
04/26/2023
First layer of gypsum and partial 2nd layer at front wall of first floor elevator.... approved

Progress Inspection Partial Pass 4/27/2023 (10:00 - 12:00) 4/27/2023 (AM) 04/27/2023
Corrections:


Miscellaneous/Other
Comment Only
04/27/2023
Remaining gypsum and fire caulking at first floor elevator,... approved 2 hour wall at north first floor stair... approved

Progress Inspection Passed 05/02/2023
Corrections:


Miscellaneous/Other
Comment Only
05/02/2023
One section of shaft wall at first floor center mechanical shaft... approved, and ok to install remaing layers of gypsum. Call and schedule inspections for remaining shaft walls as they are installed.

Progress Inspection Partial Pass 5/3/2023 (8:00 - 10:00) 5/3/2023 (AM) 05/03/2023
Corrections:


Miscellaneous/Other
Comment Only
05/03/2023
Shaft wall section at first floor center mechanical shaft... inside 2 layers of gypsum approved. See outstanding comments for redirection and and design as pertaining to this wall assembly called out on plans.

Miscellaneous/Other
Outstanding
05/03/2023
The front trash chuce wall is called out to be built with assembly, UL #415-system B. This assembly has limitations on height and cannot be stacked to the height needed and shown on plans. The designer/architect will need to be involved for redirection and design of this wall. Design to be submitted to contractor and to inspector as well.

Progress Inspection Partial Pass 05/08/2023
Corrections:


Miscellaneous/Other
Comment Only
05/08/2023
Last remaining shaft wall section to the center mechanical shaft on first floor... approved

Progress Inspection Partial Pass 5/9/2023 (10:00 - 12:00) 5/9/2023 (AM) 05/09/2023
Corrections:


Miscellaneous/Other
Comment Only
05/09/2023
Outer 2 layers of gypsum at first floor center mechanical shaft... approved.

Progress Inspection Failed 5/15/2023 (10:00 - 12:00) 5/15/2023 (AM) 05/15/2023
Corrections:


Miscellaneous/Other
Carried Forward
05/15/2023
Corrections to shaft wall at trash chute fronts. 1) all framed openings need to be tied into the wall framing of the studs and securely attached. Correct all walls floors 1-6 2) shaft wall canot be done in 2 sections for one wall, see the shaft wall design and installation guide. ( A floor needs to be one section.)

Miscellaneous/Other
Comment Only
05/15/2023
Pool rebar checked and approved pending the rebar for the steps to be installed.

Progress Inspection Failed 5/16/2023 (10:00 - 12:00) 5/16/2023 (AM) 05/16/2023
Corrections:


Miscellaneous/Other
Carried Forward
05/16/2023
Due to the assembly provided by the design professional and the wass being recessed below the gypcrete floor top and bottom plates. The shaft liner studs are not fastened to the tracks and and only attached by the fasteners of the gypsum. An alternate method of fastening the studs needs to be done to atthath the CH studs to the tracks.

Progress Inspection Partial Pass 5/23/2023 (2:30 - 3:30) 5/23/2023 (PM) 05/23/2023
Corrections:


Miscellaneous/Other
Resolved
05/23/2023
North stair 2 hr wall section needs to have studs added for the full height of wall at each end of that wall section and it needs to be tied into the top and buttom framing tracks.

Miscellaneous/Other
Comment Only
05/23/2023
Trash shaft front wall floors 4,5,&6 approved to insulate and install first layer of gypsum. Set up inspection of first layer gypsum.

Progress Inspection Not Ready 5/24/2023 (12:30 - 2:30) 5/24/2023 (PM) 05/24/2023
Corrections:


Miscellaneous/Other
Comment Only
05/24/2023
Inspection was canceled by contractor

Progress Inspection Partial Pass 5/26/2023 (8:00 - 10:00) 5/26/2023 (AM) 05/26/2023
Corrections:


Miscellaneous/Other
Comment Only
05/26/2023
1st layer of gypsum at trash room front wall on floors 5&6... approved

Progress Inspection Partial Pass 5/30/2023 (8:00 - 10:00) 5/30/2023 (AM) 05/30/2023
Corrections:


Miscellaneous/Other
Comment Only
05/30/2023
Trash shaft front wall at levels 2-6 are approved to complete gypsum covering. Reinspection of each level needed when fire stopping at second layer is completed.

Progress Inspection Partial Pass 6/2/2023 (8:00 - 10:00) 6/2/2023 (AM) 06/02/2023
Corrections:


Miscellaneous/Other
Comment Only
06/02/2023
2nd finish layer at trash shaft front wall floors 3-6, and angles at damper.... approved

Progress Inspection Passed 6/16/2023 (12:30 - 2:30) 6/16/2023 (PM) 06/16/2023
Corrections:


Miscellaneous/Other
Comment Only
06/16/2023
Front shaft wall core board framing at 1st floor trash, chute, approved.

Progress Inspection Partial Pass 6/21/2023 (12:30 - 2:30) 6/21/2023 (PM) 06/21/2023
Corrections:


Miscellaneous/Other
Comment Only
06/21/2023
First floor trash shaft outer layers of gypsum and fire angles at damper, approved. Level P1, firestops at through plank penetrations, bollard installation as needed, 4 accessible parking stalls with unloading stall between stalls, and signage. Approved

Progress Inspection Partial Pass 6/22/2023 (10:00 - 12:00) 6/22/2023 (AM) 06/22/2023
Corrections:


Miscellaneous/Other
Resolved
06/22/2023
Corrections to shaft wall at trash chute fronts. 1) all framed openings need to be tied into the wall framing of the studs and securely attached. Correct all walls floors 1-6 2) shaft wall canot be done in 2 sections for one wall, see the shaft wall design and installation guide. ( A floor needs to be one section.)

Miscellaneous/Other
Comment Only
06/22/2023
Progress finals of units... 601,603,609,611,612,613,615,616,617,618,619,620,621,622,625,525,522,521,520,519,517,515,513,512,511,509,503,501... these units are checked for final and approved, pending the adjustment of door at deck and he railing on decks to be adjusted so the opening from railing to building is not over 4".

Progress Inspection Partial Pass 6/23/2023 (8:00 - 10:00) 6/23/2023 (AM) 06/23/2023
Corrections:


Miscellaneous/Other
Resolved
06/23/2023
Due to the assembly provided by the design professional and the wass being recessed below the gypcrete floor top and bottom plates. The shaft liner studs are not fastened to the tracks and and only attached by the fasteners of the gypsum. An alternate method of fastening the studs needs to be done to atthath the CH studs to the tracks.

Miscellaneous/Other
Comment Only
06/23/2023
Ongoing final of units for the final occupancy. Units checked today include... 401,403,404,406,409,411,412,413,415,417,418,418,420,421,422,425,325,322,321,320,319,318,317,316,313. Hse units are approved, pending the decks being adjusted at the door to deck and the opening of guardrail to building being adjusted to 4" max opening. Deck railings need to also be tightened.

Progress Inspection Partial Pass 6/26/2023 (10:00 - 12:00) 6/26/2023 (AM) 06/26/2023
Corrections:


Miscellaneous/Other
Comment Only
06/26/2023
Units checked for final... 313,312,311,309,303,301,202,203,209,213,215,217,218,225. All decks need to be adjusted at railing to bldg , and bolts teghtened.

Progress Inspection Partial Pass 6/28/2023 (8:00 - 10:00) 6/28/2023 (AM) 06/28/2023
Corrections:


Miscellaneous/Other
Comment Only
06/28/2023
Additional units checked for final... units 504,506,604,606,113 Roof checked and approved, no railings needed at equipment or walkways.

Fire Inspection Final Not Ready 6/27/2023 (10:00 - 12:00) 6/27/2023 (AM) 06/28/2023
Corrections:


Miscellaneous/Other
Carried Forward
06/28/2023
Hole in ceiling 221 and 223. Door no self closing and latching: 215, 203, 110, 105 Missing smoke head in 108. Need smoke/co in 113. Ceiling needed in 112 magic boxes pack. Label first floor electrical room. 108 and 109 missing doors. Ensure all storage door closing and latching. Provide addressing. Install Knox boxes. Number doors from the front door in the clockwise direction. Change batteries in all smoke detectors as many of them are chirping. 318 and 218 smell like natural gas and should be addressed immediately. Not self closing and latching: 318, 324, 207, 216, 218 Hole in ceiling in 216. Add breaker lock in electrical panel for fire alarm panel, 6th floor trash room door not self closing and latching, 6th floor stairwell door floor 6 not closing and latching, 417, 501, 505, 510, 515, 617, 614 not closing and latching, elevator disconnects on 5th floor to be labeled at floor 1 elevator lobby, missing smoke/co in 518, s stair p-2 no storage under stair (wall off or add sprinkler head.

Progress Inspection Partial Pass 6/29/2023 (8:00 - 10:00) 6/29/2023 (AM) 06/29/2023
Corrections:


Miscellaneous/Other
Comment Only
06/29/2023
Ongoing inspection for unit final.... units looked at today and are approved # 516 & 518. Went over items that need to be done for TCO with contractor. Work is ongoing and items have been brought to the contractors attention of what need to be done for TCO.

Progress Inspection Not Ready 6/30/2023 (8:00 - 10:00) 6/30/2023 (AM) 06/30/2023
Corrections:


Miscellaneous/Other
Comment Only
06/30/2023
Ongoing inspection for the first turnover of units rented out , about half need to be rechecked due to not completed.

Progress Inspection Partial Pass 7/3/2023 (10:00 - 12:00) 7/3/2023 (AM) 07/03/2023
Corrections:


Miscellaneous/Other
Comment Only
07/03/2023
Emergency lighting tested and approved, pending the installation of 5 EM lights in various locations.... see outstanding comments. Fire doors tested with activation of alarm... approved Unit 113 checked for final and approved. Unit 402 checked for final and closer plate needs to be installed at deck railing... pending recheck for final.

Progress Inspection Partial Pass 7/5/2023 (10:00 - 12:00) 7/5/2023 (AM) 07/05/2023
Corrections:


Miscellaneous/Other
Comment Only
07/05/2023
Recheck of Emergency lights that needed to be added... light on 1st floor by unit 114, fireplace / lounge room, fitness rm, and P2 parking...approved. Checked more units for future final... 602,508,408,402,514,614,510,416,315,212,103,& 101... approved.

Progress Inspection Passed 7/6/2023 (12:30 - 2:30) 7/6/2023 (PM) 07/06/2023
Corrections:


Miscellaneous/Other
Comment Only
07/06/2023
Viewed unit 605 for future turnover.. approved These units listed are approved for TCO... 602,604,607,610,613,616,624,504,506,513,514,526,402,404,420,426,302,306,310,315,318,326,206,113. These are the units already rented out for phase one and two leases scheduled for move in before 7/20/23. Decks are blocked off due to overhead work still being done at units 526&426. Inspection is required when overhead work is completed and prior to unblocking the doors to thes unit decks. The sky lounge, pickleball court and pool deck must remained locked from any residents entering these areas since they are not finished. Inspections must be performed prior to opening these areas up to resident access.

Fire Inspection Final Partial Pass 6/28/2023 (8:00 - 10:00) 6/28/2023 (AM) 07/07/2023
Fire Inspection Final Not Ready 6/30/2023 (10:00 - 12:00) 6/30/2023 (AM) 07/07/2023
Fire Rough-in Inspection Not Ready 7/3/2023 (10:00 - 12:00) 7/3/2023 (AM) 07/07/2023
Fire Rough-in Inspection Partial Pass 7/5/2023 (10:00 - 12:00) 7/5/2023 (AM) 07/07/2023
Progress Inspection Not Ready 7/7/2023 (12:30 - 2:30) 7/7/2023 (PM) 07/07/2023
Corrections:


Miscellaneous/Other
Comment Only
07/07/2023
Inspection canceled by contractor

Progress Inspection Partial Pass 7/13/2023 (8:00 - 10:00) 7/13/2023 (AM) 07/13/2023
Corrections:


Miscellaneous/Other
Comment Only
07/13/2023
Todays inspection was to check units only for occupancy. Units on floors 3 through 6, are approved for tenant occupancy... with exception of these units listed that need reinspection. #'s 502,503,414,405,305... (closer plates needed at deck railings). Skylounge room only is also approved for tenant use.

Progress Inspection Not Ready 7/18/2023 (12:30 - 2:30) 7/18/2023 (PM) 07/18/2023
Contractor called to cancel today's inspection. jms 7/18/23
Corrections:


Miscellaneous/Other
Comment Only
07/18/2023
Inspection canceled by contractor

Progress Inspection Passed 7/19/2023 (12:30 - 2:30) 7/19/2023 (PM) 07/19/2023
Corrections:


Miscellaneous/Other
Comment Only
07/19/2023
Units 505,502,405,414,305,202,205,208,211,219,112,110,102,are approved for final and occupancy. Units 108 & 109 have been checked for final and are approved pending the installation of the entry doors... thes two units are being used for travel from front of building to back of building since site will not allow equipment or materials to be brought around the backside in order to complete the work at the pool area. These two units will need to remain in use for contractor to complete such work.

Building Final Inspection Issue TCO 9/29/2023 (8:00 - 10:00) 07/20/2023
Corrections:


Miscellaneous/Other
Carried Forward
07/20/2023
Items to be completed for the final occupancy and final of this permit. 1) completion of the pool area, pickleball court, remaining siding and decks, and the skylounge deck. All inspections must be performed by trades inspectors as required, and building inspector for approval to open these areas to the residents. 2) install occupancy signage as need for these areas. 3) Lower level parking to be cleaned out of construction materials and equipment, parking to be striped, and bollards installed as needed. 4) landscape to be completed and erosion into wetland area to be completed along with site and debris cleanup in wetland. 5) remainder of parking lot to be secnd lift of asphalt, striped and guards needed at retaining walls where guards are needed. 6) units 108, 109, 114, 115 & 116 to be inspected. 7) contractor to set up any exterior lighting , and landscape inspections with planning department. Inspections are required for completion of areas, for area turnover.

Miscellaneous/Other
Comment Only
07/20/2023
Temporary Certificate of Occupancy is granted for this building, and all units... with exception of units 108, 109, 114,115 &116 that need inspection. Conditions of issuance include: 1) any work being done over entry's or exits must have protection in place to safegard residents and public from falling debris. This includes any work above ate unit decks as well. 2) doors from units on first floor and doors to pickleball court, and skylounge deck, must remain locked until work being done at these locations has been inspected by city inspector and approved to open. See outstanding comments for other items to be completed and inspected. Call and set up inspections as areas are ready for inspection.

Building Final Inspection Partial Pass 8/18/2023 (10:00 - 12:00) 8/18/2023 (AM) 08/18/2023
Corrections:


Miscellaneous/Other
Carried Forward
09/26/2023
Items to be completed for the final occupancy and final of this permit. 1) completion of the pool area, pickleball court, remaining siding and decks, and the skylounge deck. All inspections must be performed by trades inspectors as required, and building inspector for approval to open these areas to the residents. 2) install occupancy signage as need for these areas. 3) Lower level parking to be cleaned out of construction materials and equipment, parking to be striped, and bollards installed as needed. 4) landscape to be completed and erosion into wetland area to be completed along with site and debris cleanup in wetland. 5) remainder of parking lot to be secnd lift of asphalt, striped and guards needed at retaining walls where guards are needed. 6) units 108, 109, 114, 115 & 116 to be inspected. 7) contractor to set up any exterior lighting , and landscape inspections with planning department. Inspections are required for completion of areas, for area turnover.

Miscellaneous/Other
Comment Only
08/18/2023
Stairs and railings installed at pickle board court.... items approved, and pending completion of the court itself. Railings installed at pool area, items approved. Pool area still under construction and electrical, and state pool inspection needed. Railings installed at skydeck, items approved, and pending electrical inspection approval ... this location can be turned over for public use. Inspections to be set up with the appropriate trades inspector for area turnover.

Building Final Inspection Issue CO 9/29/2023 (8:00 - 10:00) 9/29/2023 (AM) 09/29/2023
Corrections:


Miscellaneous/Other
Resolved
09/29/2023
Items to be completed for the final occupancy and final of this permit. 1) completion of the pool area, pickleball court, remaining siding and decks, and the skylounge deck. All inspections must be performed by trades inspectors as required, and building inspector for approval to open these areas to the residents. 2) install occupancy signage as need for these areas. 3) Lower level parking to be cleaned out of construction materials and equipment, parking to be striped, and bollards installed as needed. 4) landscape to be completed and erosion into wetland area to be completed along with site and debris cleanup in wetland. 5) remainder of parking lot to be secnd lift of asphalt, striped and guards needed at retaining walls where guards are needed. 6) units 108, 109, 114, 115 & 116 to be inspected. 7) contractor to set up any exterior lighting , and landscape inspections with planning department. Inspections are required for completion of areas, for area turnover.

Miscellaneous/Other
Comment Only
09/29/2023
All is completed, inspections are all done for this building. Final approved and ok to issue Final Certificate of Occupancy.

Lighting Inspection Passed 10/10/2023
Rohrs parking lot
Landscaping Inspection Passed 10/10/2023 10/10/2023
Landscaping was missing on the adjacent office building site. Re-inspected on 10.9.23 and all landscaping present.
Fire Inspection Final Passed 10/12/2023
Corrections:


Miscellaneous/Other
Outstanding
06/28/2023
Hole in ceiling 221 and 223. Door no self closing and latching: 215, 203, 110, 105 Missing smoke head in 108. Need smoke/co in 113. Ceiling needed in 112 magic boxes pack. Label first floor electrical room. 108 and 109 missing doors. Ensure all storage door closing and latching. Provide addressing. Install Knox boxes. Number doors from the front door in the clockwise direction. Change batteries in all smoke detectors as many of them are chirping. 318 and 218 smell like natural gas and should be addressed immediately. Not self closing and latching: 318, 324, 207, 216, 218 Hole in ceiling in 216. Add breaker lock in electrical panel for fire alarm panel, 6th floor trash room door not self closing and latching, 6th floor stairwell door floor 6 not closing and latching, 417, 501, 505, 510, 515, 617, 614 not closing and latching, elevator disconnects on 5th floor to be labeled at floor 1 elevator lobby, missing smoke/co in 518, s stair p-2 no storage under stair (wall off or add sprinkler head.

Fire Inspection Final Issue CO 10/12/2023