PRBD202114448
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Above Ceiling Inspection | Partial Pass | 01/14/2022 | ||
Corrections:
Miscellaneous/Other
Comment Only
01/14/2022
Above ceiling in break room approved, pending trades inspections for sprinkler, mechanical and electrical.
|
||||
Progress Inspection | Passed | 1/31/2022 (8:00 - 10:00) | 1/31/2022 (AM) | 01/31/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/31/2022
Above ceiling and fire stops for bathrooms… approved
|
||||
Fire Inspection Final | Passed | 2/25/2022 (8:00 - 10:00) | 2/25/2022 (AM) | 02/25/2022 |
Building Final Inspection | Passed | 2/25/2022 (8:00 - 10:00) | 2/25/2022 (AM) | 02/25/2022 |
Corrections:
Miscellaneous/Other
Comment Only
02/25/2022
Final approved final
|