PRBD202114796
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Partial Pass | 2/18/2022 (8:00 - 10:00) | 2/18/2022 (AM) | 02/18/2022 |
Corrections:
Miscellaneous/Other
Comment Only
02/18/2022
Consult visit… went over storefront requirements , plenum and smoke evac openings, and fireproofing, along with inspection requirements.
|
||||
Progress Inspection | Passed | 3/4/2022 (10:00 - 12:00) | 3/4/2022 (AM) | 03/04/2022 |
Corrections:
Miscellaneous/Other
Comment Only
03/04/2022
Wall framing approved, pending electrical inspection prior to covering
|
||||
Building Final Inspection | Partial Pass | 4/6/2022 (10:00 - 12:00) | 4/6/2022 (AM) | 04/06/2022 |
Corrections:
Miscellaneous/Other
Comment Only
04/06/2022
Approved to stock and train.
Complete storefront at exterior and call for electrical final with the sign at storefront. Fire final to be completed for full final.
|
||||
Building Final Inspection | Passed w/ Conditions | 4/13/2022 (12:30 - 2:30) | 4/13/2022 (PM) | 04/13/2022 |
Corrections:
Miscellaneous/Other
Comment Only
04/13/2022
Final for this permit approved and pending fire and electrical finals.
|
||||
Fire Inspection Final | Passed | 4/13/2022 (12:30 - 2:30) | 4/13/2022 (PM) | 04/13/2022 |