Permit Application Status

PRBD202114909


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202114909
Building
Finaled
THERMO KING CORPORATION
Alteration/Repair/Replace
Not Required
Interior Remodel
11/05/2021
02/24/2022
07/23/2023
01/24/2023

Locations

Permits

Permit Number: PRBD202114909

Building
Finaled
02/24/2022
07/23/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 02/25/2022
Corrections:


Miscellaneous/Other
Comment Only
02/25/2022
Wall and shafts on floors 1&2 approved. Framing for these floors has been inspected at previous times throughout the remodel process.

Framing Inspection Partial Pass 3/11/2022 (8:00 - 10:00) 3/11/2022 (AM) 03/11/2022
Corrections:


Miscellaneous/Other
Comment Only
03/11/2022
Bathrooms on 1st level… walls approved

Framing Inspection Partial Pass 3/25/2022 (8:00 - 10:00) 3/25/2022 (AM) 03/25/2022
Corrections:


Miscellaneous/Other
Comment Only
03/25/2022
Basement area A …wall framing and soffit framing approved. No covering of soffits till electrical and sprinkler inspections are completed.

Progress Inspection Partial Pass 4/29/2022 (8:00 - 10:00) 4/29/2022 (AM) 04/29/2022
Corrections:


Miscellaneous/Other
Comment Only
04/29/2022
2nd floor area “A” above ceiling and area “B”… approved

Progress Inspection Partial Pass 5/17/2022 (8:00 - 10:00) 5/17/2022 (AM) 05/17/2022
Corrections:


Miscellaneous/Other
Comment Only
05/17/2022
Area B, ceiling framing and above ceiling… approved

Framing Inspection Passed 7/25/2022 (10:00 - 12:00) 7/25/2022 (AM) 07/25/2022
Corrections:


Miscellaneous/Other
Comment Only
07/25/2022
Phase 3 front entry wall framing from 1st level, and including framing at roof front. … approved

Progress Inspection Passed 9/22/2022 (10:00 - 12:00) 9/22/2022 (AM) 09/22/2022
Corrections:


Miscellaneous/Other
Comment Only
09/22/2022
Viewed the exterior accessible ramp at front of building…approved First floor bathrooms rooms 106,141, 140,139, and second floor room 204 checked for accessibility compliance… approved

Progress Inspection Passed 10/7/2022 (12:30 - 2:30) 10/7/2022 (PM) 10/07/2022
Corrections:


Miscellaneous/Other
Outstanding
10/07/2022
1) exit signs for levels 1&2 in the cubicle areas to be adjusted and some removed so the actual exiting demarcation is not so confusing. Contractor is aware of this and knows what one’s are needed. 2) install accessibility signage at bathrooms. 3) complete handrail and guardrails and stairs at front entry. 4) occupancy signage needed at the cafeteria and auditorium rooms, contractor to verify the loads. 5) horns and strobes, and EM lighting to be tested at inspection. 6) trades inspections to be completed for all work being done and for final occupancy.

Miscellaneous/Other
Comment Only
10/07/2022
This progress inspection was to go though the spaces remodeled and verify compliance to code. Accessibility, exiting and marked signage approved. See outstanding comments for corrections and for items needed with final of this permit.

Progress Inspection Passed 10/24/2022 (8:00 - 10:00) 10/24/2022 (AM) 10/24/2022
Corrections:


Miscellaneous/Other
Comment Only
10/24/2022
EM lighting tested and approved

Progress Inspection Partial Pass 10/26/2022 (12:30 - 2:30) 10/26/2022 (PM) 10/26/2022
Corrections:


Miscellaneous/Other
Comment Only
10/26/2022
1st and 2nd levels of this remodel, approved for final and occupancy.

Building Final Inspection Passed w/ Conditions 1/3/2023 (8:00 - 10:00) 1/3/2023 (AM) 01/03/2023
Corrections:


Miscellaneous/Other
Comment Only
01/03/2023
All dampers tested and approved. Fire door at lower level is being programmed, it was not completed at time of inspection . Fire inspector will follow up with the testing of door and final for this permit is contingent on fire inspector’s approval.

Fire Inspection Final Passed 1/3/2023 (8:00 - 10:00) 1/3/2023 (AM) 01/24/2023