PRBD202115440
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 3/28/2022 (8:00 - 10:00) | 3/28/2022 (AM) | 03/28/2022 |
Corrections:
Miscellaneous/Other
Comment Only
03/28/2022
Wall framing….. all walls behind storefront approved, and can be covered after plumbing and electrical have done inspections.
See outstanding comments for correction and reinspection requirements.
|
||||
Miscellaneous/Other
Carried Forward
03/28/2022
1) beams and columns need to be patched with fireproofing that is consistent to what is already in place… Cafco Blazeshield. Call for inspection when ready and no covering of columns till inspection is completed.
2) storefront framing to be inspected, and existing mall bulkhead to be patched and sealed for smoke and gas. Call for inspection when ready and no covering at this time.
3) through floor penetrations removed in rated corridor, need to verify the patching of each floor that is being fixed to ensure the correct patching and fire stop is provided due to the penetrations removal.
4) trades inspections to be completed, call and schedule those inspections.
Call of inspections when ready. #952-563-8930 City of Bloomington Inspections.
|
||||
Progress Inspection | Passed w/ Conditions | 4/11/2022 (10:00 - 12:00) | 4/11/2022 (AM) | 04/11/2022 |
Corrections:
Miscellaneous/Other
Comment Only
04/11/2022
Fireproofing patching to existing steel approved, pending the completion of patching to steel in the storefront framing above… this location to be rechecked with the above ceiling inspection.
|
||||
Framing Inspection | Partial Pass | 4/13/2022 (10:00 - 12:00) | 4/13/2022 (AM) | 04/13/2022 |
Corrections:
Miscellaneous/Other
Resolved
04/13/2022
1) beams and columns need to be patched with fireproofing that is consistent to what is already in place… Cafco Blazeshield. Call for inspection when ready and no covering of columns till inspection is completed.
2) storefront framing to be inspected, and existing mall bulkhead to be patched and sealed for smoke and gas. Call for inspection when ready and no covering at this time.
3) through floor penetrations removed in rated corridor, need to verify the patching of each floor that is being fixed to ensure the correct patching and fire stop is provided due to the penetrations removal.
4) trades inspections to be completed, call and schedule those inspections.
Call of inspections when ready. #952-563-8930 City of Bloomington Inspections.
|
||||
Miscellaneous/Other
Comment Only
04/13/2022
Storefront framing and fireproofing patching to beams, ceilings and above ceiling…. Approved
|
||||
Fire Inspection Final | Not Ready | 5/24/2022 (10:00 - 12:00) | 5/24/2022 (AM) | 05/24/2022 |
Progress Inspection | Passed w/ Conditions | 05/24/2022 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/24/2022
Approved to bring in furnishings and stock items. This job is still under the contractor authority for any workers on-site.
No temp CO or Final at this time.
|
||||
Building Final Inspection | Not Ready | 5/24/2022 (8:00 - 10:00) | 5/24/2022 (AM) | 05/24/2022 |
Fire Inspection Final | Passed | 6/1/2022 (10:00 - 12:00) | 6/1/2022 (AM) | 06/01/2022 |
Framing Inspection | Partial Pass | 06/01/2022 | ||
Corrections:
Miscellaneous/Other
Carried Forward
06/01/2022
1) complete the exterior finishes of the store buildout on the corridor side.
2) install smoke seal at rear back of house door.
3) signage on-site, install signage as required to the locations.
Call for final when all is completed
|
||||
Miscellaneous/Other
Comment Only
06/01/2022
Approved for TCO. This space may open to the public. This permit will remain open until outstanding items listed are completed and reinspection has been done for the full final of this permit.
|
||||
Building Final Inspection | Partial Pass | 6/1/2022 (10:00 - 12:00) | 6/1/2022 (AM) | 06/01/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
06/01/2022
1) complete the exterior finishes at this buildout on the mall corridor side.
2) install smoke seal at the rear back of house door.
3) signage is on-site, install signage to all designated locations.
Call for final inspection when all is completed.
|
||||
Miscellaneous/Other
Comment Only
06/01/2022
Approved for TCO. Approval to open to the public.
See the outstanding items listed and complete them for full final. Call for final inspection when all is completed.
|
||||
Building Final Inspection | Passed | 6/10/2022 (8:00 - 10:00) | 6/10/2022 (AM) | 06/10/2022 |
Corrections:
Miscellaneous/Other
Resolved
06/10/2022
1) complete the exterior finishes at this buildout on the mall corridor side.
2) install smoke seal at the rear back of house door.
3) signage is on-site, install signage to all designated locations.
Call for final inspection when all is completed.
|
||||
Miscellaneous/Other
Comment Only
06/10/2022
All is completed, contractor to remove poly covering the smoke evac openings … (verbal to contractor)
Final approved for this permit.
|