PRBD202116172
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Building Final Inspection | Pending | |||
|
Corrections:
Miscellaneous/Other
Outstanding
04/22/2022
Need trade finals - (final approved) for A. electrical EM lighting to generator circuit is still outstanding. B. Fire final is passed final approved, BY Pete Miller, but EM lighting to the building generator circuit is still pending.C. Building final is only partial passed, due to EM lighting on the building generator circuit.
|
||||
| Framing Inspection | Passed w/ Conditions | 3/10/2022 (2:30 - 3:30) | 3/10/2022 (PM) | 03/10/2022 |
| Framing - see corrections. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
03/10/2022
Framing - steel stud. Passed.
1. Correction : electrical floor penetration from 12th to 13th floor, for future wiring. Electrician on site, install smaller diameter sleeve, fill complete gap between 2 hr concrete floor and pipe sleeve, with 2 hour intumesent fire caulk, from bottom and top sides. After future electrical is run thru new sleeve, pack mineral wool in the sleeve from bottom and top sides, and then coat both ends of sleeve with 2 hr intumesent fire caulk from bottom and top sides.
2. Correction: Remove particle board backing, and replace with FRP PLYWOOD.
3. Provide photo on phone.
|
||||
| Fire Inspection Final | Passed | 4/14/2022 (8:00 - 10:00) | 4/14/2022 (AM) | 04/14/2022 |
| Building Final Inspection | Not Ready | 4/14/2022 (8:00 - 10:00) | 4/14/2022 (AM) | 04/14/2022 |
| See corrections. | ||||
|
Corrections:
Miscellaneous/Other
Carried Forward
04/14/2022
Need trade finals - (final approved) for electrical, plumbing, hvac, prior to building final. A. Fire final is passed final approved.
|
||||
| Building Final Inspection | Partial Pass | 4/22/2022 (12:30 - 2:30) | 4/22/2022 (PM) | 04/22/2022 |
|
Corrections:
Miscellaneous/Other
Carried Forward
04/22/2022
Need trade finals - (final approved) for A. electrical EM lighting to generator circuit is still outstanding. B. Fire final is passed final approved, BY Pete Miller, but EM lighting to the building generator circuit is still pending.C. Building final is only partial passed, due to EM lighting on the building generator circuit.
|
||||