PRBD202116179
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 3/9/2022 (8:00 - 10:00) | 3/9/2022 (AM) | 03/09/2022 |
Corrections:
Miscellaneous/Other
Comment Only
03/09/2022
Wall framing of quarantine room and entry wall to the adjacent room… approved
|
||||
Framing Inspection | Partial Pass | 05/10/2022 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/10/2022
Viewed through floor penetration fire stop at ducting that will be enclosed in shaft… approved
|
||||
Framing Inspection | Not Ready | 10/17/2022 (8:00 - 10:00) | 10/17/2022 (AM) | 10/17/2022 |
Corrections:
Miscellaneous/Other
Comment Only
10/17/2022
Not ready
|
||||
Building Final Inspection | Partial Pass | 10/17/2022 (8:00 - 10:00) | 10/17/2022 (AM) | 10/17/2022 |
Corrections:
Miscellaneous/Other
Comment Only
10/17/2022
First phase of this project and permit approved, pending fire inspection approval….The quarantine room and the storage room.
Storage room… no storage within 18” of ceiling. Stored boxes need to be removed from the shelves and piles to maintain the 18” clearance.
|
||||
Fire Inspection Final | Partial Pass | 10/17/2022 (8:00 - 10:00) | 10/17/2022 (AM) | 10/17/2022 |
Framing Inspection | Passed | 11/1/2022 (10:00 - 12:00) | 11/1/2022 (AM) | 11/01/2022 |
Corrections:
Miscellaneous/Other
Comment Only
11/01/2022
Framing for classroom… approved
|
||||
Building Final Inspection | Passed w/ Conditions | 1/10/2023 (8:00 - 10:00) | 1/10/2023 (AM) | 01/10/2023 |
Corrections:
Miscellaneous/Other
Comment Only
01/10/2023
Final approved, pending removal of exit sign at door with inner swing, and pending fire testing of horn / strobes.
|
||||
Fire Inspection Final | Passed | 1/10/2023 (8:00 - 10:00) | 1/10/2023 (AM) | 01/10/2023 |