PRBD202116194
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Insulation Inspection | Pending | |||
Lath Inspection | Pending | |||
Gypsum Board/Sheet Rock Inspection | Pending | |||
Landscaping Inspection | Pending | |||
Framing Inspection | Pending | |||
Progress Inspection | Pending | |||
Footing Inspection | Pending | 6/8/2022 (12:30 - 2:30) | ||
Footing Inspection | Passed | 4/21/2022 (12:30 - 2:30) | 4/21/2022 (PM) | 04/21/2022 |
Corrections:
Miscellaneous/Other
Comment Only
04/21/2022
Strip footings and pad footings with rebar as per plans for south 1/3 of the project on Sandy gravel soil approved.
|
||||
Footing Inspection | Partial Pass | 5/10/2022 (10:00 - 12:00) | 5/10/2022 (AM) | 05/19/2022 |
Corrections:
Miscellaneous/Other
Comment Only
05/10/2022
Remaining interior footings and remaining exterior foundation walls approved. stair footings at Southwest corner approved.
|
||||
Miscellaneous/Other
Comment Only
05/19/2022
First progress inspection of foundation wall waterproofing and insulation approved. Inspection performed on May 19.
|
||||
Progress Inspection | Passed | 5/25/2022 (8:00 - 10:00) | 5/25/2022 (AM) | 05/25/2022 |
Corrections:
Miscellaneous/Other
Comment Only
05/25/2022
Progress inspection of foundation waterproofing approved.
|
||||
Footing Inspection | Not Ready | 5/31/2022 (12:30 - 2:30) | 5/31/2022 (PM) | 05/31/2022 |
Footing Inspection | Passed | 6/21/2022 (12:30 - 2:30) | 6/21/2022 (PM) | 06/21/2022 |
Corrections:
Miscellaneous/Other
Comment Only
06/21/2022
Remaining forwarding along north wall approved.
|
||||
Footing Inspection | Passed | 6/6/2022 (12:30 - 2:30) | 6/6/2022 (PM) | 07/07/2022 |
Corrections:
Miscellaneous/Other
Comment Only
07/07/2022
Under slab poly vapor barrier for east half of building approved.
|
||||
Framing Inspection | Passed | 12/7/2022 (8:00 - 10:00) | 12/7/2022 (AM) | 12/07/2022 |
Corrections:
Miscellaneous/Other
Comment Only
12/07/2022
Progress framing inspection of exterior canopies, parapets, etc. and interior second floor structural stud wall framing approved.
|
||||
Progress Inspection | Partial Pass | 1/10/2023 (12:30 - 2:30) | 1/10/2023 (PM) | 01/10/2023 |
# 4 rebar mat, for sloped concrete main floor fire truck entry aprons. Interior. Passed. Ongoing work. | ||||
Framing Inspection | Passed | 1/17/2023 (8:00 - 10:00) | 1/17/2023 (AM) | 01/17/2023 |
Corrections:
Miscellaneous/Other
Comment Only
01/17/2023
Second floor framing approved contingent on plumbing rough in approval. Second floor exterior wall insulation approved. Call for separate framing inspection of rated shaft when ready.
|
||||
Framing Inspection | Not Ready | 2/27/2023 (12:30 - 2:30) | 2/27/2023 (PM) | 02/27/2023 |
Rough In Inspection | Passed | 2/28/2023 (12:30 - 2:30) | 2/28/2023 (PM) | 02/28/2023 |
Corrections:
Miscellaneous/Other
Comment Only
02/28/2023
Framing for floor breach training OK. Progress fire caulk integrated shaft approved.
|
||||
Progress Inspection | Passed | 3/20/2023 (8:00 - 10:00) | 3/20/2023 (AM) | 03/20/2023 |
Corrections:
Miscellaneous/Other
Comment Only
03/20/2023
Final fire caulking inspection approved when remaining two unistrut penetrations are sealed. Progress framing inspection approved.
|
||||
Building Final Inspection | Partial Pass | 6/16/2023 (8:00 - 3:30) | 6/16/2023 (PM) | 06/16/2023 |
Corrections:
Miscellaneous/Other
Comment Only
06/16/2023
Use of the dispatch room, common bathrooms, garage bays and the misc adjoining rooms off the garage bays are approved for fire dept use at this time.
|
||||
Lighting Inspection | Passed | 06/25/2023 | ||
Fire Station lighting | ||||
Fire Inspection Final | Passed | 7/27/2023 (10:00 - 12:00) | 7/27/2023 (AM) | 07/27/2023 |
Building Final Inspection | Issue CO | 7/27/2023 (12:30 - 2:30) | 7/27/2023 (PM) | 07/27/2023 |
Corrections:
Miscellaneous/Other
Comment Only
07/27/2023
Submit copy of state elevator inspector‘s approval to building inspector.
|