Permit Application Status

PRBD202116194


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202116194
Building
Expired
CITY OF BLOOMINGTON
New
Not Required
Demolition of existing Fire Station #4 and construction of a new Fire Station at the same site for the City of Bloomington.
12/10/2021
04/18/2022
01/23/2024

Locations

Permits

Permit Number: PRBD202116194

Building
Expired
04/18/2022
01/23/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Insulation Inspection Pending
Lath Inspection Pending
Gypsum Board/Sheet Rock Inspection Pending
Landscaping Inspection Pending
Framing Inspection Pending
Progress Inspection Pending
Footing Inspection Pending 6/8/2022 (12:30 - 2:30)
Footing Inspection Passed 4/21/2022 (12:30 - 2:30) 4/21/2022 (PM) 04/21/2022
Corrections:


Miscellaneous/Other
Comment Only
04/21/2022
Strip footings and pad footings with rebar as per plans for south 1/3 of the project on Sandy gravel soil approved.

Footing Inspection Partial Pass 5/10/2022 (10:00 - 12:00) 5/10/2022 (AM) 05/19/2022
Corrections:


Miscellaneous/Other
Comment Only
05/10/2022
Remaining interior footings and remaining exterior foundation walls approved. stair footings at Southwest corner approved.

Miscellaneous/Other
Comment Only
05/19/2022
First progress inspection of foundation wall waterproofing and insulation approved. Inspection performed on May 19.

Progress Inspection Passed 5/25/2022 (8:00 - 10:00) 5/25/2022 (AM) 05/25/2022
Corrections:


Miscellaneous/Other
Comment Only
05/25/2022
Progress inspection of foundation waterproofing approved.

Footing Inspection Not Ready 5/31/2022 (12:30 - 2:30) 5/31/2022 (PM) 05/31/2022
Footing Inspection Passed 6/21/2022 (12:30 - 2:30) 6/21/2022 (PM) 06/21/2022
Corrections:


Miscellaneous/Other
Comment Only
06/21/2022
Remaining forwarding along north wall approved.

Footing Inspection Passed 6/6/2022 (12:30 - 2:30) 6/6/2022 (PM) 07/07/2022
Corrections:


Miscellaneous/Other
Comment Only
07/07/2022
Under slab poly vapor barrier for east half of building approved.

Framing Inspection Passed 12/7/2022 (8:00 - 10:00) 12/7/2022 (AM) 12/07/2022
Corrections:


Miscellaneous/Other
Comment Only
12/07/2022
Progress framing inspection of exterior canopies, parapets, etc. and interior second floor structural stud wall framing approved.

Progress Inspection Partial Pass 1/10/2023 (12:30 - 2:30) 1/10/2023 (PM) 01/10/2023
# 4 rebar mat, for sloped concrete main floor fire truck entry aprons. Interior. Passed. Ongoing work.
Framing Inspection Passed 1/17/2023 (8:00 - 10:00) 1/17/2023 (AM) 01/17/2023
Corrections:


Miscellaneous/Other
Comment Only
01/17/2023
Second floor framing approved contingent on plumbing rough in approval. Second floor exterior wall insulation approved. Call for separate framing inspection of rated shaft when ready.

Framing Inspection Not Ready 2/27/2023 (12:30 - 2:30) 2/27/2023 (PM) 02/27/2023
Rough In Inspection Passed 2/28/2023 (12:30 - 2:30) 2/28/2023 (PM) 02/28/2023
Corrections:


Miscellaneous/Other
Comment Only
02/28/2023
Framing for floor breach training OK. Progress fire caulk integrated shaft approved.

Progress Inspection Passed 3/20/2023 (8:00 - 10:00) 3/20/2023 (AM) 03/20/2023
Corrections:


Miscellaneous/Other
Comment Only
03/20/2023
Final fire caulking inspection approved when remaining two unistrut penetrations are sealed. Progress framing inspection approved.

Building Final Inspection Partial Pass 6/16/2023 (8:00 - 3:30) 6/16/2023 (PM) 06/16/2023
Corrections:


Miscellaneous/Other
Comment Only
06/16/2023
Use of the dispatch room, common bathrooms, garage bays and the misc adjoining rooms off the garage bays are approved for fire dept use at this time.

Lighting Inspection Passed 06/25/2023
Fire Station lighting
Fire Inspection Final Passed 7/27/2023 (10:00 - 12:00) 7/27/2023 (AM) 07/27/2023
Building Final Inspection Issue CO 7/27/2023 (12:30 - 2:30) 7/27/2023 (PM) 07/27/2023
Corrections:


Miscellaneous/Other
Comment Only
07/27/2023
Submit copy of state elevator inspector‘s approval to building inspector.