Summary

PRBD202116520
Building
Closed
ALTUS MN CENTER LLC
Alteration/Repair/Replace
Business
Remodel of existing tenant space and the connection to previously remodeled space. Involves removing some walls, floor covering and ceiling (tiles)
12/20/2021
01/06/2022
09/06/2022

Locations

Permits

Permit Number: PRBD202116520

Building
Expired
01/06/2022
09/06/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Building Final Inspection Pending
Corrections:


Miscellaneous/Other
Outstanding
03/10/2022
Complete installation of conference rooms glass walls and call for reinspection. 90 day temporary occupancy approved.

Framing Inspection Passed 2/9/2022 (10:00 - 12:00) 2/9/2022 (AM) 02/09/2022
Corrections:


Miscellaneous/Other
Comment Only
02/09/2022
Phase 2 framing approved.

Fire Inspection Final Failed 3/9/2022 (10:00 - 12:00) 3/9/2022 (AM) 03/09/2022
Corrections:


Miscellaneous/Other
Outstanding
03/09/2022
Sprinkler inspection not completed.

Building Final Inspection Failed 3/9/2022 (10:00 - 12:00) 3/9/2022 (AM) 03/09/2022
Corrections:


Miscellaneous/Other
Carried Forward
03/09/2022
Need final fire approval. Complete installation of glass conference room walls. Call for reinspection.

Fire Inspection Final Passed 3/10/2022 (8:00 - 10:00) 3/10/2022 (AM) 03/10/2022
Corrections:


Miscellaneous/Other
Outstanding
03/09/2022
Sprinkler inspection not completed.

Building Final Inspection Issue TCO 3/10/2022 (10:00 - 12:00) 3/10/2022 (AM) 03/10/2022
Corrections:


Miscellaneous/Other
Resolved
03/10/2022
Need final fire approval. Complete installation of glass conference room walls. Call for reinspection.

Miscellaneous/Other
Carried Forward
03/10/2022
Complete installation of conference rooms glass walls and call for reinspection. 90 day temporary occupancy approved.