PRBD202116520
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
03/10/2022
Complete installation of conference rooms glass walls and call for reinspection. 90 day temporary occupancy approved.
|
||||
Framing Inspection | Passed | 2/9/2022 (10:00 - 12:00) | 2/9/2022 (AM) | 02/09/2022 |
Corrections:
Miscellaneous/Other
Comment Only
02/09/2022
Phase 2 framing approved.
|
||||
Fire Inspection Final | Failed | 3/9/2022 (10:00 - 12:00) | 3/9/2022 (AM) | 03/09/2022 |
Corrections:
Miscellaneous/Other
Outstanding
03/09/2022
Sprinkler inspection not completed.
|
||||
Building Final Inspection | Failed | 3/9/2022 (10:00 - 12:00) | 3/9/2022 (AM) | 03/09/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
03/09/2022
Need final fire approval. Complete installation of glass conference room walls. Call for reinspection.
|
||||
Fire Inspection Final | Passed | 3/10/2022 (8:00 - 10:00) | 3/10/2022 (AM) | 03/10/2022 |
Corrections:
Miscellaneous/Other
Outstanding
03/09/2022
Sprinkler inspection not completed.
|
||||
Building Final Inspection | Issue TCO | 3/10/2022 (10:00 - 12:00) | 3/10/2022 (AM) | 03/10/2022 |
Corrections:
Miscellaneous/Other
Resolved
03/10/2022
Need final fire approval. Complete installation of glass conference room walls. Call for reinspection.
|
||||
Miscellaneous/Other
Carried Forward
03/10/2022
Complete installation of conference rooms glass walls and call for reinspection. 90 day temporary occupancy approved.
|