PRBD202200062
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 1/14/2022 (8:00 - 10:00) | 1/14/2022 (AM) | 01/14/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/14/2022
Wall framing approved
|
||||
Fire Inspection Final | Passed | 7/1/2022 (8:00 - 10:00) | 7/1/2022 (AM) | 07/01/2022 |
Corrections:
Miscellaneous/Other
Comment Only
07/01/2022
No sprinkler work done at this space, coverage is still in effect. Fire extinguisher is at stockroom outer wall. Final approved
|
||||
Building Final Inspection | Passed w/ Conditions | 7/1/2022 (7:00 - 8:00) | 7/1/2022 (AM) | 07/01/2022 |
Corrections:
Miscellaneous/Other
Comment Only
07/01/2022
2- 8ft walls were installed for stockroom… This is all this permit is for.
New permit is required for corporate to install new fixtures and complete this space buildout.
|