PRBD202200088
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 3/23/2022 (10:00 - 12:00) | 3/23/2022 (AM) | 03/23/2022 |
Corrections:
Miscellaneous/Other
Comment Only
03/23/2022
First framing inspection of walls to include studios, rooms 156 and 135, approved.
|
||||
Footing Inspection | Passed | 3/30/2022 (10:00 - 12:00) | 3/30/2022 (AM) | 03/30/2022 |
Corrections:
Miscellaneous/Other
Comment Only
03/30/2022
Interior footings for elevator pit and miscellaneous mezzanine columns approved.
|
||||
Footing Inspection | Passed | 4/5/2022 (10:00 - 12:00) | 4/5/2022 (AM) | 04/05/2022 |
Corrections:
Miscellaneous/Other
Comment Only
04/05/2022
Remaining pad footings and pad extensions approved.
|
||||
Framing Inspection | Passed | 6/22/2022 (8:00 - 10:00) | 6/22/2022 (AM) | 06/22/2022 |
Corrections:
Miscellaneous/Other
Comment Only
06/22/2022
Framing of photo studio walls approved.
|
||||
Framing Inspection | Passed | 7/14/2022 (10:00 - 12:00) | 7/14/2022 (AM) | 07/14/2022 |
Corrections:
Miscellaneous/Other
Comment Only
07/14/2022
Mezzanine framing approved.
|
||||
Progress Inspection | Passed | 10/7/2022 (8:00 - 10:00) | 10/7/2022 (AM) | 10/07/2022 |
Corrections:
Miscellaneous/Other
Comment Only
10/07/2022
Above ceiling inspection approved. Note, contractor to submit specifications sheet showing fire rating of sound baffling material installed at deck level.
|
||||
Progress Inspection | Not Ready | 11/14/2022 (12:30 - 2:30) | 11/14/2022 (PM) | 11/14/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
11/14/2022
Progress inspection towards final occupancy requirements, mezzanine level off limits to all tenant employees. Main level OK to install all furniture and equipment. Temporary certificate of occupancy would require compliant guard rails on mezzanine level. Call for inspection when ready.
|
||||
Progress Inspection | Passed w/ Conditions | 1/3/2023 (8:00 - 10:00) | 1/3/2023 (AM) | 01/03/2023 |
Corrections:
Miscellaneous/Other
Outstanding
11/14/2022
Progress inspection towards final occupancy requirements, mezzanine level off limits to all tenant employees. Main level OK to install all furniture and equipment. Temporary certificate of occupancy would require compliant guard rails on mezzanine level. Call for inspection when ready.
|
||||
Miscellaneous/Other
Outstanding
01/03/2023
Racking in gear room approved. Complete framing and gyp. board at elevator shaft and call for fire caulk inspection.
|
||||
Building Final Inspection | Issue TCO | 2/24/2023 (8:00 - 10:00) | 2/24/2023 (AM) | 02/24/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
02/24/2023
1. Provide letter of approval from state elevator inspector regarding new elevators. 2. Provide cane guard at drinking fountain as discussed. 3. Need final fire approval. 4. 15 day temporary C.O. approved.
|
||||
Fire Inspection Final | Passed | 2/22/2023 (8:00 - 10:00) | 08/15/2023 | |
Building Final Inspection | Passed | 09/19/2024 | ||
Corrections:
Miscellaneous/Other
Resolved
09/19/2024
1. Provide letter of approval from state elevator inspector regarding new elevators. 2. Provide cane guard at drinking fountain as discussed. 3. Need final fire approval. 4. 15 day temporary C.O. approved.
|