Summary

PRBD202200124
Building
Finaled
BLMGTN SCHOOL DIST #271
Alteration/Repair/Replace
Educational
Complete remodel of Hillcrest Community School. Work includes installation of new chiller, construction of new chiller enclosure, installation of new chilled water piping, new hot water piping, replacement of boilers with new, replacement of AHU with new, replacement of flooring, replacement of lights, replacement of electrical sub panels, replacement of ceilings, bathroom remodel, window replacement, plumbing upgrades, kitchen remodel, construction of new walls and installation of new casework.
01/05/2022
05/23/2022
04/23/2023
10/24/2022

Locations

Permits

Permit Number: PRBD202200124

Building
Finaled
05/23/2022
04/23/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Passed 5/25/2022 (7:00 - 8:00) 5/25/2022 (AM) 05/25/2022
Corrections:


Miscellaneous/Other
Comment Only
05/25/2022
Addition footings. WF5-0 rebar and footing approved for concrete placement

Framing Inspection Passed 7/25/2022 (8:00 - 10:00) 7/25/2022 (AM) 07/25/2022
A. Metal stud soffit framing - passed. B. Walk thru with Rich Putman - Krause Anderson. C. Building has no fire rated separation for the size and use. D. Classroom doors not installed. D. Exterior glass windows on exterior walls, are coming soon.
Progress Inspection Partial Pass 8/18/2022 (12:30 - 2:30) 8/18/2022 (PM) 08/16/2022
Progress: 1. New Tempered glass. 2. Classrooms. 3. Kitchen w/ new and existing appliances. Environmental health. 4. Fire alarm testing and progress. 5. Restrooms w/ new gender stalls. 6. Mechanical - existing and new. temp occupancy, new chiller has not arrived, will use existing chiller as temp for AC, for teacher move in week.7. Accessibility - interior/exterior.
Above Ceiling Inspection Passed w/ Conditions 08/22/2022
Above ceiling building inspections, passed. A. See fire sprinkler system layout - Call for fire marshal above ceiling inspections, for existing and modified new sprinkler, and kitchen equipment with
Building Final Inspection Passed w/ Conditions 8/25/2022 (10:00 - 12:00) 8/25/2022 (AM) 08/25/2022
August 25, 2022. Building permit final - passed with conditions.
Corrections:


Miscellaneous/Other
Outstanding
08/25/2022
August 25, 2022. All trade final inspections, and fire marshal final inspections, are required, prior to the Building final inspection to close the building permit. Permission to occupy is granted today by the city of Bloomington. Pending items: 1. Accessible restrooms signage pending. 2. Mechanical final balance report pending. 3. Fire marshal final pending. 4. All other trade inspections and Environmental health final.

Fire Inspection Final Partial Pass 8/25/2022 (10:00 - 12:00) 8/25/2022 (AM) 08/30/2022
Fire Inspection Final Passed 10/5/2022 10/24/2022