Permit Application Status

PRBD202201013


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202201013
Building
Finaled
SOUTHTOWN OFFICE PARK LLP
Alteration/Repair/Replace
Business
Remodel of existing office space.
01/31/2022
02/16/2022
11/02/2022
05/06/2022

Locations

Permits

Permit Number: PRBD202201013

Building
Finaled
02/16/2022
11/02/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed w/ Conditions 3/18/2022 (8:00 - 10:00) 3/18/2022 (AM) 03/18/2022
Corrections:


Miscellaneous/Other
Outstanding
03/18/2022
Framing - passed. A. Provide for all other required rough in trade inspections.( fire sprinkler, electrical.)

Fire Inspection Final Passed 5/6/2022 (8:00 - 10:00) 5/6/2022 (AM) 05/06/2022
Building Final Inspection Passed w/ Conditions 5/6/2022 (8:00 - 10:00) 5/6/2022 (AM) 05/06/2022
Building final - suite 425. A. Contingent upon Pete Miller - fire inspection final.