PRBD202201936
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Passed w/ Conditions | 4/8/2022 (10:00 - 12:00) | 4/8/2022 (AM) | 04/08/2022 |
| See corrections. | ||||
|
Corrections:
Miscellaneous/Other
Outstanding
04/08/2022
Framing - passed. A. Please call for above ceiling inspection PRIOR TO INSTALLING CEILING TILES...for (fire sprinkler, building inspector, electrical, mechanical, and low voltage. B. FRAMING IS PASSED TO COVER WITH THE CONDITIONS listed above. *** C. CALL FOR REIN-SPECTION FOR BUILDING INSPECTOR, after the above is completed, and prior to installing ceiling tiles.
|
||||
| Building Final Inspection | Passed w/ Conditions | 7/12/2022 (10:00 - 12:00) | 7/12/2022 (AM) | 07/12/2022 |
| Building Final - passed with conditions that all trade inspections permits are final approved. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
07/12/2022
Building Final - passed, with conditions all trade inspections are final approved.
|
||||
| Fire Inspection Final | Passed | 7/12/2022 (10:00 - 12:00) | 7/12/2022 (AM) | 07/12/2022 |