Permit Application Status

PRBD202202089


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202202089
Building
Finaled
IKEA PROPERTY INC
Alteration/Repair/Replace
Not Required
INTERIOR ALTERATION LIMITED TO DEMOLISHING EXISTING NON LOAD BEARING MODULAR PARTITIONS, FLOORING, AND ASSOCIATED ELECTRICAL DEVICES AND INSTALLING NEW TO MATCH EXISTING IN NEW CONFIGURATION
03/02/2022
06/05/2023
11/06/2024
05/10/2024

Locations

Permits

Permit Number: PRBD202202089

Building
Finaled
06/05/2023
11/06/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection VOID 7/6/2023 (AM) 07/06/2023
Progress Inspection Passed 7/31/2023 (10:00 - 12:00) 7/31/2023 (AM) 07/31/2023
Corrections:


Miscellaneous/Other
Comment Only
07/31/2023
Progress inspection... First phase wall sections have been removed and in process of relocating walls to the layout of the plans provided. Exit signs are also being changed out throughout the building.

Progress Inspection Passed 8/22/2023 (10:00 - 12:00) 8/22/2023 (AM) 08/22/2023
Corrections:


Miscellaneous/Other
Comment Only
08/22/2023
Progress of the wall installation and layout completed for phase 1 area. Exiting signage is being swithed out and approved.

Progress Inspection Passed 11/20/2023 (8:00 - 10:00) 11/20/2023 (AM) 11/20/2023
Corrections:


Miscellaneous/Other
Comment Only
11/20/2023
Completion of phase one area, all exiting and fire extinguishers installed and approved

Progress Inspection Passed 1/18/2024 (12:30 - 2:30) 1/18/2024 (PM) 01/18/2024
Corrections:


Miscellaneous/Other
Comment Only
01/18/2024
Viewed area of completed remodel, exiting and marking/ signage is in place and approved.

Building Final Inspection Passed 5/9/2024 (12:30 - 2:30) 5/9/2024 (PM) 05/09/2024
Corrections:


Miscellaneous/Other
Comment Only
05/09/2024
Final approved for the scope of work and permit.

Fire Inspection Final Passed 5/9/2024 (12:30 - 2:30) 5/9/2024 (PM) 05/10/2024