PRBD202202298
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 4/1/2022 (10:00 - 12:00) | 4/1/2022 (AM) | 04/01/2022 |
Corrections:
Miscellaneous/Other
Comment Only
04/01/2022
Walls… framing approved.
Storefront and inventory room ceiling needs to be inspected by electrical and fire, prior to covering.
|
||||
Progress Inspection | Passed | 05/18/2022 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/18/2022
Approval given to stock and bring in furnishings. Call for all finals when ready and completed.
|
||||
Building Final Inspection | Not Ready | 5/18/2022 (12:30 - 2:30) | 5/18/2022 (PM) | 05/18/2022 |
Corrections:
Miscellaneous/Other
Comment Only
05/18/2022
Not ready for final. See the progress inspection report with conditions of stocking.
|
||||
Fire Inspection Final | Passed | 5/23/2022 (8:00 - 10:00) | 5/23/2022 (AM) | 05/23/2022 |
Building Final Inspection | Partial Pass | 5/23/2022 (8:00 - 10:00) | 5/23/2022 (AM) | 05/23/2022 |
Corrections:
Miscellaneous/Other
Comment Only
05/23/2022
Approval to stock and setup space.
Storefront needs to be completed and finished, all finishes to be installed.
Rear door to have locking mechanism installed, it does need to be able to push and release without special knowledge or action for exiting space.
|
||||
Building Final Inspection | Passed | 5/26/2022 (12:30 - 2:30) | 5/26/2022 (PM) | 05/26/2022 |
Corrections:
Miscellaneous/Other
Comment Only
05/26/2022
Work completed… final approved and ok to open to public.
|