PRBD202202841
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Failed | 7/8/2022 (8:00 - 10:00) | 7/8/2022 (AM) | 07/08/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
07/08/2022
This was a progress framing inspection, and the long soffit framing is what was viewed.
This long soffit does not have enough support from what framing will be left after all ductwork is installed.
A new method of support is need for this soffit, as contractor proposed… it could be a supported box header , or support by stiff backs at framing and unistrut attached to bar joists… or by other means per the design professional.
Contractor and designer to come up with a solution to remedy this issue and have on-site for the inspector at inspection.
|
||||
Framing Inspection | Partial Pass | 7/26/2022 (8:00 - 10:00) | 7/26/2022 (AM) | 07/26/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
07/26/2022
This was a progress framing inspection, and the long soffit framing is what was viewed.
This long soffit does not have enough support from what framing will be left after all ductwork is installed.
A new method of support is need for this soffit, as contractor proposed… it could be a supported box header , or support by stiff backs at framing and unistrut attached to bar joists… or by other means per the design professional.
Contractor and designer to come up with a solution to remedy this issue and have on-site for the inspector at inspection.
|
||||
Miscellaneous/Other
Carried Forward
07/26/2022
Corrections…
1) Cleat over-notched stud in hallway and provide clearance or sleeve at hole where Plastic piping runs through stud in the hallway location.
2) provide support detail to long soffit , no covering of adjoining wall or soffit at this time. Storefront to be completed as well. Set up inspection when these two areas are ready.
|
||||
Miscellaneous/Other
Comment Only
07/26/2022
Walls for interior of space approved to cover. No covering of storefront, soffit, or the adjoining wall at this time.
|
||||
Above Ceiling Inspection | Partial Pass | 8/1/2022 (12:30 - 2:30) | 8/1/2022 (PM) | 08/01/2022 |
Corrections:
Miscellaneous/Other
Comment Only
08/01/2022
Restroom and office ceilings framing approved, pending electrical and sprinkler inspections prior to covering.
|
||||
Framing Inspection | Partial Pass | 8/8/2022 (8:00 - 10:00) | 8/8/2022 (AM) | 08/08/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
08/08/2022
This was a progress framing inspection, and the long soffit framing is what was viewed.
This long soffit does not have enough support from what framing will be left after all ductwork is installed.
A new method of support is need for this soffit, as contractor proposed… it could be a supported box header , or support by stiff backs at framing and unistrut attached to bar joists… or by other means per the design professional.
Contractor and designer to come up with a solution to remedy this issue and have on-site for the inspector at inspection.
|
||||
Miscellaneous/Other
Resolved
08/08/2022
Corrections…
1) Cleat over-notched stud in hallway and provide clearance or sleeve at hole where Plastic piping runs through stud in the hallway location.
2) provide support detail to long soffit , no covering of adjoining wall or soffit at this time. Storefront to be completed as well. Set up inspection when these two areas are ready.
|
||||
Miscellaneous/Other
Comment Only
08/08/2022
Approved to cover the sides of storefront soffit and misc open walls where plumbing was added.
The long soffit now has a fix provided by the designer, complete this fix and set up inspection.
|
||||
Framing Inspection | Passed | 9/9/2022 (8:00 - 10:00) | 9/9/2022 (AM) | 09/09/2022 |
Corrections:
Miscellaneous/Other
Resolved
09/09/2022
This was a progress framing inspection, and the long soffit framing is what was viewed.
This long soffit does not have enough support from what framing will be left after all ductwork is installed.
A new method of support is need for this soffit, as contractor proposed… it could be a supported box header , or support by stiff backs at framing and unistrut attached to bar joists… or by other means per the design professional.
Contractor and designer to come up with a solution to remedy this issue and have on-site for the inspector at inspection.
|
||||
Miscellaneous/Other
Comment Only
09/09/2022
Supporting of the center soffit completed and approved. Ok to cover this framing and remaining storefront once fire inspection has viewed the sprinklers.
|
||||
Above Ceiling Inspection | Partial Pass | 9/26/2022 (8:00 - 10:00) | 9/26/2022 (AM) | 09/26/2022 |
Corrections:
Miscellaneous/Other
Comment Only
09/26/2022
Ceiling framing and above ceiling at front half of space approved.
Note… fire proofing patching needed at back half of space, call for above ceiling inspection when ready.
|
||||
Above Ceiling Inspection | Passed | 10/24/2022 (10:00 - 12:00) | 10/24/2022 (AM) | 10/24/2022 |
Corrections:
Miscellaneous/Other
Comment Only
10/24/2022
Above ceiling approved
|
||||
Fire Inspection Final | Failed | 10/28/2022 (8:00 - 10:00) | 10/28/2022 (AM) | 10/28/2022 |
Building Final Inspection | Not Ready | 10/28/2022 (8:00 - 10:00) | 10/28/2022 (AM) | 10/28/2022 |
Corrections:
Miscellaneous/Other
Comment Only
10/28/2022
Inspection canceled, not ready.
|
||||
Progress Inspection | Passed w/ Conditions | 11/08/2022 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/08/2022
Pending EH approval, this space buildout is approved to bring in stock and setup the space, and allow staff for training purposes only.
Set up final inspections when all trades are fully completed and work is done to space.
|
||||
Building Final Inspection | Failed | 11/8/2022 (12:30 - 2:30) | 11/8/2022 (PM) | 11/08/2022 |
Corrections:
Miscellaneous/Other
Comment Only
11/08/2022
See progress inspection dated 11/8/22. Not ready for temp or final C.O. at this point of the buildout.
Call in all final inspections with trades permits and set up inspections with fire, EH, and building, for final inspection when space is ready for turnover.
|
||||
Fire Inspection Final | Partial Pass | 11/8/2022 (12:30 - 2:30) | 11/8/2022 (PM) | 11/08/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
11/08/2022
Replace all missing ceiling tiles, tag Ansul system, chain carbon dioxide tanks, install fire extinguishers front and back of house, abc and k class in kitchen, and uncover smoke detector.
|
||||
Building Final Inspection | Not Ready | 11/15/2022 (2:30 - 3:30) | 11/15/2022 (PM) | 11/15/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
11/15/2022
1) final reports from 3rd party electrical inspection to be submitted to electrical inspection.
2) install door to bathroom.
3) temp cashwrap in place.install spec’d wrap for final
ReSet up final inspection to allow electrical inspector time to view reports.
|
||||
Building Final Inspection | Passed w/ Conditions | 11/16/2022 (12:30 - 2:30) | 11/16/2022 (PM) | 11/16/2022 |
Corrections:
Miscellaneous/Other
Resolved
11/16/2022
1) final reports from 3rd party electrical inspection to be submitted to electrical inspection.
2) install door to bathroom.
3) temp cashwrap in place.install spec’d wrap for final
ReSet up final inspection to allow electrical inspector time to view reports.
|
||||
Miscellaneous/Other
Comment Only
11/16/2022
Final for this buildout is approved on condition of follow up inspection with environmental health for operations and equipment.
|
||||
Fire Inspection Final | Passed | 11/15/2022 (2:30 - 3:30) | 11/15/2022 (PM) | 11/16/2022 |
Corrections:
Miscellaneous/Other
Outstanding
11/08/2022
Replace all missing ceiling tiles, tag Ansul system, chain carbon dioxide tanks, install fire extinguishers front and back of house, abc and k class in kitchen, and uncover smoke detector.
|