PRBD202203445
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed w/ Conditions | 4/29/2022 (10:00 - 12:00) | 4/29/2022 (AM) | 04/29/2022 |
Framing passed with conditions. | ||||
Corrections:
Miscellaneous/Other
Outstanding
04/29/2022
Need above ceiling trade inspections for 1.City of Bloomington, fire sprinkler above ceiling inspection by fire marshal, 2. Electrical low voltage above ceiling inspection. 3. Patch in missing drywall on interior of suite above ceiling, drywall is missing or removed be trade contractors. 4. Mechanical permits for new is required.
|
||||
Above Ceiling Inspection | Passed | 5/16/2022 (10:00 - 12:00) | 5/16/2022 (AM) | 05/16/2022 |
Need exit sign and EM lighting upon final. | ||||
Corrections:
Miscellaneous/Other
Comment Only
05/16/2022
A. Need Emergency lighting( EM LIGHTING) in space, onto building emergency generator circuit upon final.
B. Final fire was issued, and final approved, on rough in inspection.
C. Building inspector to verify EM lighting FUNCTIONING upon final inspection.
|
||||
Building Final Inspection | Passed w/ Conditions | 6/1/2022 (8:00 - 10:00) | 6/1/2022 (AM) | 06/01/2022 |
See corrections. | ||||
Corrections:
Miscellaneous/Other
Comment Only
06/01/2022
Final building inspection - passed. A. Need AM fire alarm test - this week.
|
||||
Fire Inspection Final | Passed | 6/1/2022 (8:00 - 10:00) | 6/1/2022 (AM) | 06/02/2022 |