Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 5/11/2022 (7:00 - 8:00) | 5/11/2022 (AM) | 05/11/2022 |
Corrections:
Miscellaneous/Other
Comment Only
05/11/2022
Framing approved.
|
||||
Framing Inspection | Passed | 5/19/2022 (12:30 - 2:30) | 5/19/2022 (PM) | 05/19/2022 |
Corrections:
Miscellaneous/Other
Comment Only
05/19/2022
Framing, fire stops and floor core prep for concrete patching… approved
|
||||
Framing Inspection | Partial Pass | 06/09/2022 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/09/2022
Storefront entry framing approved, pending installation of bracing installation to framing above ceiling to support framed ceiling of storefront.
Mall bulkhead cannot support framing of ceiling.
|
||||
Building Final Inspection | Not Ready | 6/9/2022 (8:00 - 10:00) | 6/9/2022 (AM) | 06/09/2022 |
Corrections:
Miscellaneous/Other
Comment Only
06/09/2022
Approved to bring in tools and other stock.
Call for final when all is completed. Not ready for final inspection yet.
|
||||
Building Final Inspection | Not Ready | 6/17/2022 (12:30 - 2:30) | 6/17/2022 (PM) | 06/17/2022 |
Corrections:
Miscellaneous/Other
Comment Only
06/17/2022
Inspection canceled
|
||||
Building Final Inspection | Not Ready | 6/21/2022 (12:30 - 2:30) | 6/21/2022 (PM) | 06/21/2022 |
Corrections:
Miscellaneous/Other
Comment Only
06/21/2022
Complete installations and space finishes. Corrections given by Environmental Health to be addressed to allow a TCO or permit final.
|
||||
Building Final Inspection | Passed | 6/24/2022 (12:30 - 2:30) | 6/24/2022 (PM) | 06/24/2022 |
Corrections:
Miscellaneous/Other
Comment Only
06/24/2022
Final approved, and approved for occupancy… pending final corrections with EH and their follow up inspection, and licensing.
|
||||
Fire Inspection Final | Passed | 6/24/2022 (10:00 - 12:00) | 6/24/2022 (AM) | 06/27/2022 |