Permit Application Status

PRBD202203573


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202203573
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Repair/Replace
Not Required
Tenant finish improvements - E356
04/07/2022
05/06/2022
12/24/2022
06/27/2022

Locations

Permits

Permit Number: PRBD202203573

Building
Finaled
05/06/2022
12/24/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 5/11/2022 (7:00 - 8:00) 5/11/2022 (AM) 05/11/2022
Corrections:


Miscellaneous/Other
Comment Only
05/11/2022
Framing approved.

Framing Inspection Passed 5/19/2022 (12:30 - 2:30) 5/19/2022 (PM) 05/19/2022
Corrections:


Miscellaneous/Other
Comment Only
05/19/2022
Framing, fire stops and floor core prep for concrete patching… approved

Framing Inspection Partial Pass 06/09/2022
Corrections:


Miscellaneous/Other
Comment Only
06/09/2022
Storefront entry framing approved, pending installation of bracing installation to framing above ceiling to support framed ceiling of storefront. Mall bulkhead cannot support framing of ceiling.

Building Final Inspection Not Ready 6/9/2022 (8:00 - 10:00) 6/9/2022 (AM) 06/09/2022
Corrections:


Miscellaneous/Other
Comment Only
06/09/2022
Approved to bring in tools and other stock. Call for final when all is completed. Not ready for final inspection yet.

Building Final Inspection Not Ready 6/17/2022 (12:30 - 2:30) 6/17/2022 (PM) 06/17/2022
Corrections:


Miscellaneous/Other
Comment Only
06/17/2022
Inspection canceled

Building Final Inspection Not Ready 6/21/2022 (12:30 - 2:30) 6/21/2022 (PM) 06/21/2022
Corrections:


Miscellaneous/Other
Comment Only
06/21/2022
Complete installations and space finishes. Corrections given by Environmental Health to be addressed to allow a TCO or permit final.

Building Final Inspection Passed 6/24/2022 (12:30 - 2:30) 6/24/2022 (PM) 06/24/2022
Corrections:


Miscellaneous/Other
Comment Only
06/24/2022
Final approved, and approved for occupancy… pending final corrections with EH and their follow up inspection, and licensing.

Fire Inspection Final Passed 6/24/2022 (10:00 - 12:00) 6/24/2022 (AM) 06/27/2022