PRBD202203699
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 6/10/2022 (10:00 - 12:00) | 6/10/2022 (AM) | 06/10/2022 |
Corrections:
Miscellaneous/Other
Comment Only
06/10/2022
Framing of corridor wall, BOH wall and furred wall approved and ok to cover. Leave open the electrical runs for the electrical inspection… once approved they can be closed.
Call for storefront framing when ready.
|
||||
Framing Inspection | Failed | 6/23/2022 (8:00 - 10:00) | 6/23/2022 (AM) | 06/23/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
06/23/2022
1) Complete mall bulkhead infill where old corridor was removed and relocated. This bulkhead must be of 1 hour construction and sealed for smoke and gas.
2) Install framing under main entry box beam header.
Call for inspection when completed, no covering at this time.
|
||||
Framing Inspection | Passed | 6/27/2022 (12:30 - 2:30) | 6/27/2022 (PM) | 06/27/2022 |
Corrections:
Miscellaneous/Other
Outstanding
06/23/2022
1) Complete mall bulkhead infill where old corridor was removed and relocated. This bulkhead must be of 1 hour construction and sealed for smoke and gas.
2) Install framing under main entry box beam header.
Call for inspection when completed, no covering at this time.
|
||||
Miscellaneous/Other
Comment Only
06/27/2022
Storefront framing approved to cover pending inspection approval for electrical and sprinkler.
|
||||
Building Final Inspection | Failed | 7/15/2022 (10:00 - 12:00) | 7/15/2022 (AM) | 07/15/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
07/15/2022
Not ready for final.
Corrections…
1)Install front gate door.
2) fire stop penetrations at rated corridor wall , both sides.
3) card reader box needs to be a rated box, change out the mud ring opening.
Complete work at this space, all trades inspections to be performed and finals needed when going for a building final. Call for inspections.
|
||||
Fire Inspection Final | Not Ready | 7/15/2022 (10:00 - 12:00) | 7/15/2022 (AM) | 07/19/2022 |
Building Final Inspection | Partial Pass | 7/26/2022 (8:00 - 10:00) | 7/26/2022 (AM) | 07/26/2022 |
Corrections:
Miscellaneous/Other
Resolved
07/26/2022
Not ready for final.
Corrections…
1)Install front gate door.
2) fire stop penetrations at rated corridor wall , both sides.
3) card reader box needs to be a rated box, change out the mud ring opening.
Complete work at this space, all trades inspections to be performed and finals needed when going for a building final. Call for inspections.
|
||||
Miscellaneous/Other
Carried Forward
07/26/2022
1) install accessibility signage to fitting room
2) fix rear door to shut and latch, and new smoke seal
3) intumescent paint the access doors to rolling gates.
|
||||
Miscellaneous/Other
Comment Only
07/26/2022
Approved for temp final. Call for reinspection final of the outstanding comments listed in this inspection.
|
||||
Fire Inspection Final | Passed | 7/26/2022 (8:00 - 10:00) | 7/26/2022 (AM) | 07/26/2022 |
Building Final Inspection | Passed | 8/1/2022 (10:00 - 12:00) | 8/1/2022 (AM) | 08/01/2022 |
Corrections:
Miscellaneous/Other
Resolved
08/01/2022
1) install accessibility signage to fitting room
2) fix rear door to shut and latch, and new smoke seal
3) intumescent paint the access doors to rolling gates.
|
||||
Miscellaneous/Other
Comment Only
08/01/2022
Corrections are completed.
Flame stop 2 was used to cover the wood access doors to gate, two coats to each door.
Items corrected… final approved.
|