Permit Application Status

PRBD202205258


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202205258
Building
Finaled
LIFESPACE COMMUNITIES INC
Alteration/Repair/Replace
Not Required
This is the next phase of the Friendship Village development. The work includes removal of (3) existing wings and renovation of approximately 14,000 sf of existing space into R3 and A2 occupancies with connection to the existing campus buildings by a new link to the new healthcare building.
05/11/2022
08/12/2022
07/29/2024
01/31/2024

Locations

Permits

Permit Number: PRBD202205258

Building
Finaled
08/12/2022
07/29/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Passed 9/29/2022 (8:00 - 10:00) 9/29/2022 (AM) 09/29/2022
Corrections:


Miscellaneous/Other
Comment Only
09/29/2022
Footing for link connection as per plans approved.

Footing Inspection Passed 10/10/2022 (12:30 - 2:30) 10/10/2022 (PM) 10/11/2022
Corrections:


Miscellaneous/Other
Comment Only
10/11/2022
Progress inspection of strip footings for stoops approved.

Footing Inspection Passed 10/12/2022 (10:00 - 12:00) 10/12/2022 (AM) 10/12/2022
Corrections:


Miscellaneous/Other
Comment Only
10/12/2022
Second progress inspection on poured walls and footings for stoops approved.

Miscellaneous/Other
Comment Only
10/13/2022
10-13-22: Strip footings for two stoops at West end and foundation wall for stoop on north side approved.

Footing Inspection Passed 10/14/2022 (10:00 - 12:00) 10/14/2022 (AM) 10/14/2022
Corrections:


Miscellaneous/Other
Comment Only
10/14/2022
Poured foundation walls for stoops on the west side approved.

Footing Inspection Passed 10/24/2022 (10:00 - 12:00) 10/24/2022 (AM) 10/24/2022
Corrections:


Miscellaneous/Other
Comment Only
10/24/2022
Footings for pergola and barbecue area approved.

Footing Inspection Passed 10/26/2022 (10:00 - 12:00) 10/26/2022 (AM) 10/26/2022
Corrections:


Miscellaneous/Other
Comment Only
10/26/2022
Rebar for three stoop landings approved.

Progress Inspection Passed 1/26/2023 (12:30 - 2:30) 1/26/2023 (PM) 01/26/2023
Progress Inspection Passed 2/9/2023 (10:00 - 12:00) 2/9/2023 (AM) 02/09/2023
Corrections:


Miscellaneous/Other
Comment Only
02/09/2023
Progress inspection on fire caulking and spray foam insulation of deck approved.

Progress Inspection Passed 2/24/2023 (10:00 - 12:00) 2/24/2023 (AM) 02/27/2023
Corrections:


Miscellaneous/Other
Comment Only
02/27/2023
Above ceiling fire caulk at East wing units approved.

Progress Inspection Not Ready 2/28/2023 (10:00 - 12:00) 2/28/2023 (AM) 02/28/2023
Corrections:


Miscellaneous/Other
Comment Only
02/28/2023
Waiting for electrical rough in approval above ceiling in East wing. Call when ready.

Progress Inspection Passed 3/2/2023 (10:00 - 12:00) 3/2/2023 (AM) 03/03/2023
Corrections:


Miscellaneous/Other
Comment Only
03/03/2023
Above ceiling insulation in two east units approved.

Progress Inspection Passed 3/9/2023 (10:00 - 12:00) 3/9/2023 (AM) 03/09/2023
Corrections:


Miscellaneous/Other
Comment Only
03/09/2023
Progress inspection of office framing area and overhead insulation of common areas approved.

Progress Inspection Passed 3/17/2023 (10:00 - 12:00) 3/17/2023 (AM) 03/17/2023
Corrections:


Miscellaneous/Other
Comment Only
03/17/2023
Progress inspection of miscellaneous framing and insulation approved.

Progress Inspection Passed 3/21/2023 (10:00 - 12:00) 3/21/2023 (AM) 03/21/2023
Corrections:


Miscellaneous/Other
Comment Only
03/21/2023
Progress inspection of miscellaneous framing approved.

Progress Inspection Passed 3/28/2023 (10:00 - 12:00) 3/28/2023 (AM) 03/28/2023
Corrections:


Miscellaneous/Other
Comment Only
03/28/2023
Remaining above ceiling insulation in lobby area approved.

Progress Inspection Partial Pass 4/4/2023 (12:30 - 2:30) 4/4/2023 (PM) 04/04/2023
Progress Inspection Passed w/ Conditions 4/7/2023 (2:30 - 3:30) 4/7/2023 (PM) 04/07/2023
Corrections:


Miscellaneous/Other
Comment Only
04/07/2023
Patch fire proofing on existing structural steel in connecting link. Confirm corrections at framing inspection for link.

Progress Inspection Passed 4/14/2023 (12:30 - 2:30) 4/14/2023 (PM) 04/14/2023
Corrections:


Miscellaneous/Other
Comment Only
04/14/2023
Remaining framing in link approved. Call for fire proofing patching inspection when ready.

Progress Inspection Passed 4/19/2023 (2:30 - 3:30) 4/19/2023 (PM) 04/20/2023
Corrections:


Miscellaneous/Other
Comment Only
04/20/2023
Fire proofing patching approved. Remaining framing approved.

Progress Inspection Passed 5/16/2023 (10:00 - 12:00) 5/16/2023 (AM) 05/16/2023
Corrections:


Miscellaneous/Other
Comment Only
05/16/2023
Preliminary final inspection to review potential items needing attention. On track for final inspections scheduled later this week.

Progress Inspection Passed 5/17/2023 (10:00 - 12:00) 5/17/2023 (AM) 05/17/2023
Corrections:


Miscellaneous/Other
Comment Only
05/17/2023
Meeting on site to review final inspections progression with project manager.

Progress Inspection Passed 5/18/2023 (10:00 - 12:00) 5/18/2023 (AM) 05/18/2023
Corrections:


Miscellaneous/Other
Comment Only
05/18/2023
30 day temporary certificate of occupancy approved for two living units, offices and common areas. Call four separate final for kitchen.

Progress Inspection Partial Pass 5/23/2023 (10:00 - 12:00) 5/23/2023 (AM) 05/23/2023
Corrections:


Miscellaneous/Other
Comment Only
05/23/2023
Reviewed progress on outstanding open final items to be completed.

Progress Inspection Passed 6/28/2023 (8:00 - 10:00) 6/28/2023 (AM) 06/28/2023
Building Final Inspection Passed 06/28/2023
Fire Inspection Final Passed 01/31/2024