PRBD202205685
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 9/13/2022 (8:00 - 10:00) | 9/13/2022 (AM) | 09/13/2022 |
Corrections:
Miscellaneous/Other
Comment Only
09/13/2022
Wall framing approved.
Call for ceiling framing and fitting rooms framing when ready.
|
||||
Framing Inspection | Partial Pass | 09/15/2022 | ||
Corrections:
Miscellaneous/Other
Comment Only
09/15/2022
Hard lid Ceilings ok to cover.
Above ceiling approved
|
||||
Framing Inspection | Passed | 9/22/2022 (8:00 - 10:00) | 9/22/2022 (AM) | 09/22/2022 |
Corrections:
Miscellaneous/Other
Comment Only
09/22/2022
Fitting rooms wall framing approved
|
||||
Above Ceiling Inspection | Passed | 10/24/2022 (10:00 - 12:00) | 10/24/2022 (AM) | 10/24/2022 |
Corrections:
Miscellaneous/Other
Comment Only
10/24/2022
Above ceiling and ceiling framing approved … ok to pad out.
|
||||
Building Final Inspection | Partial Pass | 11/28/2022 (10:00 - 12:00) | 11/28/2022 (AM) | 11/28/2022 |
Corrections:
Miscellaneous/Other
Comment Only
11/28/2022
EM lighting verified and approved.
Approved to stock and setup space. See outstanding comments for correction and final inspection requirements.
|
||||
Miscellaneous/Other
Comment Only
11/28/2022
Correction…
1) install accessibility signage to fitting room.
Call for final inspection when all setup is completed
|
||||
Fire Inspection Final | Passed | 11/28/2022 (10:00 - 12:00) | 11/28/2022 (AM) | 11/28/2022 |
Building Final Inspection | Passed | 12/2/2022 (12:30 - 2:30) | 12/2/2022 (PM) | 12/02/2022 |
Corrections:
Miscellaneous/Other
Comment Only
12/02/2022
Final approved, ok to open
|