PRBD202205931
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Passed | 4/12/2023 (12:30 - 2:30) | 4/12/2023 (PM) | 04/12/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/12/2023
Progress inspection of first floor framing atmechanical and electrical rooms OK. Confirm rating requirements for various rooms on first floor to allow for proper sheet rock applications. Progress framing inspection of miscellaneous second floor and roof parapet approved.
|
||||
| Framing Inspection | Passed | 5/23/2023 (8:00 - 10:00) | 5/23/2023 (AM) | 05/23/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/23/2023
Framing at chiller room wall approved. Framing at rated wall at HPM approved. First floor fire caulking of miscellaneous rated walls approved. Mid to high roof framing approved.
|
||||
| Progress Inspection | Passed | 5/26/2023 (10:00 - 12:00) | 5/26/2023 (AM) | 05/26/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/26/2023
Meeting on site to confirm exit lighting revisions with superintendent and architect.
|
||||
| Framing Inspection | Passed | 9/15/2023 (10:00 - 12:00) | 9/15/2023 (AM) | 09/15/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/15/2023
Framing for phase 1 of walkway and west and approved.
|
||||
| Framing Inspection | Passed | 9/26/2023 (8:00 - 10:00) | 9/26/2023 (AM) | 09/26/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/26/2023
Remaining framing on Skyway, East end, approved.
|
||||
| Framing Inspection | Passed | 3/7/2025 (8:00 - 10:00) | 3/7/2025 (AM) | 03/07/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/07/2025
Progress inspection of framing and sheet rock of rated walls throughout approved.
|
||||
| Progress Inspection | Passed | 3/31/2025 (8:00 - 10:00) | 3/31/2025 (AM) | 03/31/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/31/2025
Progress inspection of remaining framing issues and sheet rock on walls approved.
|
||||
| Framing Inspection | Passed | 10/22/2025 (8:00 - 10:00) | 10/22/2025 (AM) | 10/22/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/22/2025
Pre-final progress inspection to review job site and discuss final approvals procedures, approved.
|
||||
| Framing Inspection | Passed | 11/25/2025 (8:00 - 10:00) | 11/25/2025 (AM) | 11/25/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/25/2025
Conversion of one hour corridor wall to two hour in existing building approved. Note, fire caulking on existing one layer side OK to keep as is.
|
||||
| Building Final Inspection | Partial Pass | 2/2/2026 (8:00 - 10:00) | 2/2/2026 (AM) | 02/02/2026 |
| Pre Final [Lee\, Jake @ 01/15/2026 12:38 PM] | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
02/02/2026
Pre-final walk-through shows no outstanding issues.
|
||||
| Building Final Inspection | Passed | 2/5/2026 (10:00 - 12:00) | 2/5/2026 (AM) | 02/05/2026 |
| Fire Inspection Final | Passed w/ Conditions | 2/5/2026 (10:00 - 12:00) | 2/5/2026 (AM) | 02/05/2026 |