Permit Application Status

PRBD202205931


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202205931
Building
Permit(s) Issued
SEAGATE TECHNOLOGY INC
Addition
Not Required
The balance of construction, not including previously approved foundations.
05/25/2022
08/23/2022
09/27/2025

Locations

Permits

Permit Number: PRBD202205931

Building
Expired
08/23/2022
09/27/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Pending
Insulation Inspection Pending
Lath Inspection Pending
Fire Inspection Final Pending
Building Final Inspection Pending
Framing Inspection Passed 4/12/2023 (12:30 - 2:30) 4/12/2023 (PM) 04/12/2023
Corrections:


Miscellaneous/Other
Comment Only
04/12/2023
Progress inspection of first floor framing atmechanical and electrical rooms OK. Confirm rating requirements for various rooms on first floor to allow for proper sheet rock applications. Progress framing inspection of miscellaneous second floor and roof parapet approved.

Framing Inspection Passed 5/23/2023 (8:00 - 10:00) 5/23/2023 (AM) 05/23/2023
Corrections:


Miscellaneous/Other
Comment Only
05/23/2023
Framing at chiller room wall approved. Framing at rated wall at HPM approved. First floor fire caulking of miscellaneous rated walls approved. Mid to high roof framing approved.

Progress Inspection Passed 5/26/2023 (10:00 - 12:00) 5/26/2023 (AM) 05/26/2023
Corrections:


Miscellaneous/Other
Comment Only
05/26/2023
Meeting on site to confirm exit lighting revisions with superintendent and architect.

Framing Inspection Passed 9/15/2023 (10:00 - 12:00) 9/15/2023 (AM) 09/15/2023
Corrections:


Miscellaneous/Other
Comment Only
09/15/2023
Framing for phase 1 of walkway and west and approved.

Framing Inspection Passed 9/26/2023 (8:00 - 10:00) 9/26/2023 (AM) 09/26/2023
Corrections:


Miscellaneous/Other
Comment Only
09/26/2023
Remaining framing on Skyway, East end, approved.

Framing Inspection Passed 3/7/2025 (8:00 - 10:00) 3/7/2025 (AM) 03/07/2025
Corrections:


Miscellaneous/Other
Comment Only
03/07/2025
Progress inspection of framing and sheet rock of rated walls throughout approved.

Progress Inspection Passed 3/31/2025 (8:00 - 10:00) 3/31/2025 (AM) 03/31/2025
Corrections:


Miscellaneous/Other
Comment Only
03/31/2025
Progress inspection of remaining framing issues and sheet rock on walls approved.