PRBD202208423
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Partial Pass | 4/4/2023 (10:00 - 12:00) | 4/4/2023 (AM) | 04/04/2023 |
200 Lyndale Ave. Tommy’s car wash. (Footing First pour) east end working west | ||||
Footing Inspection | Partial Pass | 4/17/2023 (10:00 - 12:00) | 4/17/2023 (AM) | 04/17/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/17/2023
Pad footing at line 14, grid B
3 pad footings on grid C, lines 12,13,14
Footing off line 15, between grids C and B.7
Line 15&16 from grids A to D.5
Line A, 13-16
Grid B, line 13 to approximately line 5
Rebar in trench drain from line 14, to approximately line 5.
|
||||
Footing Inspection | Partial Pass | 4/21/2023 (8:00 - 10:00) | 4/21/2023 (AM) | 04/21/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/21/2023
Piers on grid C , lines 11,12,13,&14
Perimeter walls and piers on lines 15&16, and grids A and B on the already placed footings.
Pad on grid B, line 14.
Approved
|
||||
Footing Inspection | Passed | 4/28/2023 (7:00 - 8:00) | 4/28/2023 (AM) | 04/28/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/28/2023
Inspection of all the remaining footings and pads on north end of building, from line 5 on grid B, around and back to line 5 of grid D.
Pad foooting on line 1 grid B. And pad footings on grid F, lines 1.8 & 3.2.
Approved for concrete placement.
|
||||
Progress Inspection | Passed | 05/26/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/26/2023
Underslab poly... approved
|
||||
Housewrap Inspection | Partial Pass | 07/14/2023 | ||
Corrections:
Miscellaneous/Other
Carried Forward
07/14/2023
Tyvek housewrap installed, contractor has the wrap nailed off in most places per the tyvek requirements. Contractor to finish adding capped fasteners where missing at the corner wall sections.
|
||||
Framing Inspection | Failed | 08/24/2023 | ||
Corrections:
Miscellaneous/Other
Carried Forward
08/24/2023
As per metal stud framing requirements, flanges on each side of stud need to be fastened to top and bottom tracks.
There are many studs at the exterior side of building that are not fastened to bottom track around the perimeter of building walls.
The inner flange is also not fastened to bottom track around perimeter walls.
Where unable to fasten studs, a metal clip can be used that anchors to stud and is shot or screwed to concrete... see stud manufacturer requirements for the proper metal clips.
Interior framing also follows the same requirements.
Studs are fastened on only one side where both sides need to be fastened. Slotted bottom track used in place of 1" track, the studs will still need to be fastened to both sides of the stud flanges in track. Deep leg track used but not for deflection where used, will also require studs to be fastened at bottom flanges and at top tracks.
Call for reinspection when this has been corrected.
|
||||
Housewrap Inspection | Passed | 09/07/2023 | ||
Corrections:
Miscellaneous/Other
Resolved
09/07/2023
Tyvek housewrap installed, contractor has the wrap nailed off in most places per the tyvek requirements. Contractor to finish adding capped fasteners where missing at the corner wall sections.
|
||||
Miscellaneous/Other
Comment Only
09/07/2023
Housewrap approved
|
||||
Framing Inspection | Passed | 09/07/2023 | ||
Corrections:
Miscellaneous/Other
Resolved
09/07/2023
As per metal stud framing requirements, flanges on each side of stud need to be fastened to top and bottom tracks.
There are many studs at the exterior side of building that are not fastened to bottom track around the perimeter of building walls.
The inner flange is also not fastened to bottom track around perimeter walls.
Where unable to fasten studs, a metal clip can be used that anchors to stud and is shot or screwed to concrete... see stud manufacturer requirements for the proper metal clips.
Interior framing also follows the same requirements.
Studs are fastened on only one side where both sides need to be fastened. Slotted bottom track used in place of 1" track, the studs will still need to be fastened to both sides of the stud flanges in track. Deep leg track used but not for deflection where used, will also require studs to be fastened at bottom flanges and at top tracks.
Call for reinspection when this has been corrected.
|
||||
Miscellaneous/Other
Comment Only
09/07/2023
Framing approved
|
||||
Progress Inspection | Passed | 9/7/2023 (8:00 - 10:00) | 9/7/2023 (AM) | 09/07/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/07/2023
Framing approved, corrections with fastening have been completed.
|
||||
Lighting Inspection | Passed | 11/6/2023 | 11/07/2023 | |
Tommy's lighting | ||||
Landscaping Inspection | Passed | 11/15/2023 | 11/14/2023 | |
Building Final Inspection | Failed | 11/30/2023 (12:30 - 2:30) | 11/30/2023 (PM) | 11/30/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
11/30/2023
Trades permits to be final inspected, plumbing and mechanical... Water lines to be marked, and RPZs to be tested and marked. Mechanical needs documentation of installation venting and boiler to be running for inspection.
Fire inspection needed for the pending alarm permit and signage marking for fire inspection.
Building permit.... change out toilet tank to either a top mount flush or right hand flush and add trap wrap to hand sink.
No temp or final at this time, call infor all needed .
|
||||
Fire Inspection Final | Passed | 11/30/2023 (12:30 - 2:30) | 11/30/2023 (PM) | 12/01/2023 |
Building Final Inspection | Issue TCO | 12/01/2023 | ||
Corrections:
Miscellaneous/Other
Resolved
12/01/2023
Trades permits to be final inspected, plumbing and mechanical... Water lines to be marked, and RPZs to be tested and marked. Mechanical needs documentation of installation venting and boiler to be running for inspection.
Fire inspection needed for the pending alarm permit and signage marking for fire inspection.
Building permit.... change out toilet tank to either a top mount flush or right hand flush and add trap wrap to hand sink.
No temp or final at this time, call infor all needed .
|
||||
Miscellaneous/Other
Comment Only
12/01/2023
Approved for Temp occupancy, pending.... mechanical final and reinspection for building final
|
||||
Building Final Inspection | Issue CO | 12/12/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
12/12/2023
All inspections and permits associated with this buildout completed. Approved to issue Certificate of Occupancy
|