PRBD202209683
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Pending | |||
Fire Inspection Final | Pending | |||
Insulation Inspection | Passed | 12/12/2022 (12:30 - 2:30) | 12/12/2022 (PM) | 12/12/2022 |
Rebar, R-10 HIGH DENSITY RIGID 4X8 FT, 2 INCH THICK, REBAR #4 grid - 16 inch on center each way. | ||||
Building Final Inspection | Passed w/ Conditions | 5/18/2023 (12:30 - 2:30) | 5/18/2023 (PM) | 05/18/2023 |
Corrections:
Miscellaneous/Other
Comment Only
05/18/2023
Final building and all trade inspections. Passed. (Pass with conditions, to allow for any revisions under same building permit.)
|
||||
Fire Inspection Final | Partial Pass | 5/18/2023 (12:30 - 2:30) | 5/18/2023 (PM) | 05/18/2023 |
Verify what lights are on generator power. |