PRBD202210156
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 12/9/2022 (8:00 - 10:00) | 12/9/2022 (AM) | 12/09/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
12/09/2022
Corrections…
1) all the fire stops going through floor at all plumbing need to have the foam removed and the proper fire caulking used for the fire stops.
Leave walls open for reinspection.
2) the back wall of the bathrooms is not properly secured at wall top and at ends of wall. Install metal framing to attach wall to.
These corrections will need to be reinspected, call to schedule this reinspection…. #952-563-8930
|
||||
Miscellaneous/Other
Comment Only
12/09/2022
Wall framing is approved. Ok to cover areas without plumbing. See outstanding comments for corrections and reinspection.
|
||||
Framing Inspection | Partial Pass | 12/09/2022 | ||
Corrections:
Miscellaneous/Other
Carried Forward
12/09/2022
Corrections…
1) all the fire stops going through floor at all plumbing need to have the foam removed and the proper fire caulking used for the fire stops.
Leave walls open for reinspection.
2) the back wall of the bathrooms is not properly secured at wall top and at ends of wall. Install metal framing to attach wall to.
These corrections will need to be reinspected, call to schedule this reinspection…. #952-563-8930
|
||||
Miscellaneous/Other
Comment Only
12/09/2022
Amendment to inspection report.
Approval to insulate and cover only walls that have been approved by electrical inspection, and walls that do not have any electrical or plumbing in them. This does not include the vestibule or the framed soffits.
Complete all trades work and call for inspections. Framing inspection to be called in when trades inspections are approved by inspection.
|
||||
Framing Inspection | Passed | 12/14/2022 (12:30 - 2:30) | 12/14/2022 (PM) | 12/14/2022 |
Corrections:
Miscellaneous/Other
Resolved
12/14/2022
Corrections…
1) all the fire stops going through floor at all plumbing need to have the foam removed and the proper fire caulking used for the fire stops.
Leave walls open for reinspection.
2) the back wall of the bathrooms is not properly secured at wall top and at ends of wall. Install metal framing to attach wall to.
These corrections will need to be reinspected, call to schedule this reinspection…. #952-563-8930
|
||||
Miscellaneous/Other
Comment Only
12/14/2022
Corrections with wall framing and fire stops at plumbing… approved.
Ok to cover walls.
|
||||
Fire Inspection Final | Failed | 3/13/2023 (12:30 - 2:30) | 3/13/2023 (PM) | 03/13/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
03/13/2023
No permit pull and no sprinkler inspections completed. Add exit signs and emergency lighting. Ceiling tiles must me installed and sprinkler protection maintained.
|
||||
Building Final Inspection | Failed | 3/13/2023 (12:30 - 2:30) | 3/13/2023 (PM) | 03/13/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
03/13/2023
1) install exit signs with EM lighting as per discussion with contractor.
2) correct accessible signage to bathrooms.
3) obtain sprinkler permit and inspections for final.
Will allow to occupy space on a temporary basis and under supervision. Call for inspections when these corrections are completed.
|
||||
Building Final Inspection | Passed w/ Conditions | 5/17/2023 (2:30 - 3:30) | 5/17/2023 (PM) | 05/17/2023 |
Corrections:
Miscellaneous/Other
Resolved
05/17/2023
1) install exit signs with EM lighting as per discussion with contractor.
2) correct accessible signage to bathrooms.
3) obtain sprinkler permit and inspections for final.
Will allow to occupy space on a temporary basis and under supervision. Call for inspections when these corrections are completed.
|
||||
Miscellaneous/Other
Comment Only
05/17/2023
Final approved pending installation of Occupancy sign.
|
||||
Fire Inspection Final | Passed | 5/17/2023 (2:30 - 3:30) | 5/17/2023 (PM) | 05/17/2023 |
Corrections:
Miscellaneous/Other
Outstanding
03/13/2023
No permit pull and no sprinkler inspections completed. Add exit signs and emergency lighting. Ceiling tiles must me installed and sprinkler protection maintained.
|