PRBD202210606
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Landscaping Inspection | Pending | |||
Lighting Inspection | Pending | |||
Lath Inspection | Pending | |||
Building Final Inspection | Pending | 5/24/2024 (8:00 - 10:00) | 5/24/2024 (AM) | |
Fire Inspection Final | Pending | 5/24/2024 (8:00 - 10:00) | 5/24/2024 (AM) | |
Walk-through Inspection | Passed | 4/21/2023 (12:30 - 2:30) | 4/21/2023 (PM) | 04/21/2023 |
Miscellaneous/Other
Resolved
04/21/2023
Final progress inspection approved. Submit pile cap location drawing to plan review department when ready. Call for final inspection when ready.
|
||||
Miscellaneous/Other
Comment Only
04/21/2023
Met on site to review schedule and phasing of start up of construction of Toyota in two phases.
|
||||
Progress Inspection | Passed | 5/18/2023 (10:00 - 12:00) | 5/18/2023 (AM) | 05/18/2023 |
Miscellaneous/Other
Comment Only
05/18/2023
First progress inspection of hoist collars placed prior to concrete pour approved.
|
||||
Progress Inspection | Passed | 6/26/2023 (2:30 - 3:30) | 6/26/2023 (PM) | 06/26/2023 |
Miscellaneous/Other
Comment Only
06/26/2023
Progress inspection of rebar for poured slab approved.
|
||||
Rough In Inspection | Passed | 7/31/2023 (12:30 - 2:30) | 7/31/2023 (PM) | 07/31/2023 |
Miscellaneous/Other
Comment Only
07/31/2023
Post tension cabling for phase 1 on second floor approved.
|
||||
Progress Inspection | Passed | 9/7/2023 (12:30 - 2:30) | 9/7/2023 (PM) | 09/07/2023 |
Miscellaneous/Other
Comment Only
09/07/2023
Final post tension slab inspection for east side of roof approved.
|
||||
Framing Inspection | Passed | 9/22/2023 (8:00 - 10:00) | 9/22/2023 (AM) | 09/22/2023 |
Miscellaneous/Other
Comment Only
09/22/2023
Progress inspection of exterior wall framing on third level approved.
|
||||
Progress Inspection | Passed | 11/27/2023 (10:00 - 12:00) | 11/27/2023 (AM) | 11/27/2023 |
Miscellaneous/Other
Comment Only
11/27/2023
Progress on two hour shaft on second floor approved.
|
||||
Insulation Inspection | Passed | 11/29/2023 (12:30 - 2:30) | 11/29/2023 (PM) | 11/29/2023 |
Miscellaneous/Other
Comment Only
11/29/2023
Second progress inspection of rated shaft on second floor approved. Progress inspection of One hour rated walls of mechanical room on second floor approved. Exterior wall foam insulation on the second floor approved.
|
||||
Above Ceiling Inspection | Passed | 12/12/2023 (12:30 - 2:30) | 12/12/2023 (PM) | 12/12/2023 |
Miscellaneous/Other
Comment Only
12/12/2023
Progress inspection of rated shaft on third floor approved. Insulation exterior walls on third floor approved.
|
||||
Gypsum Board/Sheet Rock Inspection | Passed | 12/20/2023 (10:00 - 12:00) | 12/20/2023 (AM) | 12/20/2023 |
Miscellaneous/Other
Comment Only
12/20/2023
Second floor framing, and above ceiling approved.
|
||||
Progress Inspection | Passed | 1/25/2024 (10:00 - 12:00) | 1/25/2024 (AM) | 01/25/2024 |
Miscellaneous/Other
Comment Only
01/25/2024
Overall progress inspection of all floors to review needs for final inspections in phases and to review surrounding property in preparation for coming finals.
|
||||
Progress Inspection | Passed | 2/1/2024 (12:30 - 2:30) | 2/1/2024 (PM) | 02/01/2024 |
Miscellaneous/Other
Comment Only
02/01/2024
Remaining miscellaneous framing, details approved.
|
||||
Building Final Inspection | Partial Pass | 3/28/2024 (10:00 - 12:00) | 3/28/2024 (AM) | 03/28/2024 |
Miscellaneous/Other
Comment Only
03/28/2024
Partial occupancy approved for southern service garage only to be occupied by employees only.
|
||||
Progress Inspection | Passed | 4/12/2024 (10:00 - 12:00) | 4/12/2024 (AM) | 04/12/2024 |
Miscellaneous/Other
Comment Only
04/12/2024
Partial occupancy approved to bring in fixtures and furniture. Call for final when ready.
|