PRBD202210937
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 9/27/2022 (12:30 - 2:30) | 9/27/2022 (PM) | 09/27/2022 |
Corrections:
Miscellaneous/Other
Comment Only
09/27/2022
Wall framing approved, pending trades inspections prior to covering.
|
||||
Building Final Inspection | Partial Pass | 10/18/2022 (12:30 - 2:30) | 10/18/2022 (PM) | 10/18/2022 |
Corrections:
Miscellaneous/Other
Comment Only
10/18/2022
Approved to stock and set up space.
See outstanding comments for final inspection and permit final.
|
||||
Miscellaneous/Other
Carried Forward
10/18/2022
1) complete finishes at storefront
2) install trap wrap at bath sink.
3) corrections per EH to be completed.
Call for final inspections when ready, also schedule EH and fire inspection for their finals.
|
||||
Fire Inspection Final | Partial Pass | 10/18/2022 (12:30 - 2:30) | 10/18/2022 (PM) | 10/20/2022 |
Building Final Inspection | Passed w/ Conditions | 10/24/2022 (12:30 - 2:30) | 10/24/2022 (PM) | 10/24/2022 |
Corrections:
Miscellaneous/Other
Resolved
10/24/2022
1) complete finishes at storefront
2) install trap wrap at bath sink.
3) corrections per EH to be completed.
Call for final inspections when ready, also schedule EH and fire inspection for their finals.
|
||||
Miscellaneous/Other
Comment Only
10/24/2022
Space is completed as per the plans submitted. Final approved pending fire inspection final and EH requirements and final.
|
||||
Fire Inspection Final | Passed | 10/24/2022 (12:30 - 2:30) | 10/24/2022 (PM) | 10/24/2022 |