PRBD202212630
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Above Ceiling Inspection | Passed | 3/9/2023 (10:00 - 12:00) | 3/9/2023 (AM) | 03/09/2023 |
Corrections:
Miscellaneous/Other
Comment Only
03/09/2023
Ceiling framing and above ceiling approved.
Pending inspection by fire and mechanical inspections (with approvals), ok to cover.
|
||||
Framing Inspection | Passed w/ Conditions | 3/9/2023 (10:00 - 12:00) | 3/9/2023 (AM) | 03/09/2023 |
Corrections:
Miscellaneous/Other
Comment Only
03/09/2023
Walls and ceiling framing and storefront, approved… covering of walls and ceilings is pending the outcome approval by all respective trades inspections scheduled for 3/10/23.
Contractor to to have plumbing pipe through floor fire stoppped, inspector will allow photo of fire stopped pipe.
Putty packs are required for the 3 electrical boxes installed within the membrane of the rated shaft wall. Inspector will allow photos of this from the contractor as well.
|
||||
Building Final Inspection | Passed | 5/24/2023 (10:00 - 12:00) | 5/24/2023 (AM) | 05/24/2023 |
Corrections:
Miscellaneous/Other
Comment Only
05/24/2023
Final approved, ok to finish stocking and open to public.
|
||||
Fire Inspection Final | Passed | 5/24/2023 (10:00 - 12:00) | 5/24/2023 (PM) | 05/24/2023 |