PRBD202213677
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Partial Pass | 12/22/2022 (8:00 - 10:00) | 12/22/2022 (AM) | 12/22/2022 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/22/2022
Framing approved pending fire inspection for sprinklers.
Correction… install access panel in location to reach junction boxes and shutoff valves.
|
||||
| Fire Inspection Final | Passed | 1/24/2023 (12:30 - 2:30) | 1/24/2023 (PM) | 01/24/2023 |
| Building Final Inspection | Failed | 1/25/2023 (10:00 - 12:00) | 1/25/2023 (AM) | 01/25/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/25/2023
Not ready for final.
Have all trades inspections and finals completed, and final clean up also to be done. Reschedule final inspection with building and EH when all is done and ready for final inspection.
|
||||
| Building Final Inspection | Not Ready | 1/30/2023 (2:30 - 3:30) | 1/30/2023 (PM) | 01/30/2023 |
| Canceled 1/30 and moved to 2/1. Thanks- VM | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
01/30/2023
Inspection canceled by contractor
|
||||
| Building Final Inspection | Passed w/ Conditions | 2/1/2023 (8:00 - 10:00) | 2/1/2023 (AM) | 02/01/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/01/2023
Final approved pending full final from Environmental Health. A temp has been given by Environmental Health with a reinspection to be scheduled.
|
||||