Permit Application Status

PRBD202215588


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202215588
Building
Finaled
JUNO INVESTMENTS LLC
Alteration/Repair/Replace
Business
Remove and replace carpet, remove and replace ceiling tile. Redo breakrooms ,redo plumbing to break rooms. enlarge bathrooms. Remove and replace office walls. tile work
12/21/2022
01/10/2023
10/29/2023
05/02/2023

Locations

Permits

Permit Number: PRBD202215588

Building
Finaled
01/10/2023
10/29/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 2/21/2023 (8:00 - 10:00) 2/21/2023 (AM) 02/21/2023
Framing : walk thru all 3 levels. A. Contractor to patch, refasten, replace missing, all missing gypsum above ceiling for corridor rating. CALL for above ceiling reinspection for all missing gypsum! B. ALL Conference rooms require horn strobes ( C. Call for above ceiling for all 3 levels inspection for gypsum )
Framing Inspection Passed 3/28/2023 (2:30 - 3:30) 3/28/2023 (PM) 03/28/2023
Fire Inspection Final Passed 4/26/2023 (12:30 - 2:30) 4/26/2023 (PM) 04/26/2023
Building Final Inspection Passed 4/27/2023 (2:30 - 3:30) 4/27/2023 (PM) 04/27/2023
Suite 300, complete floor. New doors, finishes, break rooms.