Permit Application Status

PRBD202215692


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202215692
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Repair/Replace
Not Required
The intent of the scope contained within these documents relates to the interior build-out of a mercantile space contained within an existing shopping center. Proposed work includes construction and installation of new non-load bearing partitions, fixtures, finishes, lighting, mechanical, electrical, and plumbing.
12/27/2022
03/02/2023
10/18/2023
04/21/2023

Locations

Permits

Permit Number: PRBD202215692

Building
Finaled
03/02/2023
10/18/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed w/ Conditions 3/22/2023 (8:00 - 10:00) 3/22/2023 (AM) 03/22/2023
Corrections:


Miscellaneous/Other
Comment Only
03/22/2023
Wall and ceiling framing approved. Call for fire inspection of sprinklers when installed, no covering ceilings till inspected and approved.

Building Final Inspection Partial Pass 4/17/2023 (8:00 - 10:00) 4/17/2023 (AM) 04/17/2023
Corrections:


Miscellaneous/Other
Carried Forward
04/17/2023
1) install the glass for the fitting room doors 2) install trap wrap on bathroom sink 3) front stoe sign to be installed and inspected by electrical inspection

Miscellaneous/Other
Comment Only
04/17/2023
Approved for temp occupancy. Complete the outstanding items listed and call for final inspection.

Fire Inspection Final Issue TCO 4/17/2023 (8:00 - 10:00) 4/17/2023 (AM) 04/17/2023
Building Final Inspection Passed 4/20/2023 (10:00 - 12:00) 4/20/2023 (AM) 04/20/2023
Corrections:


Miscellaneous/Other
Resolved
04/20/2023
1) install the glass for the fitting room doors 2) install trap wrap on bathroom sink 3) front stoe sign to be installed and inspected by electrical inspection

Miscellaneous/Other
Comment Only
04/20/2023
Final for this buildout and permit... approved

Fire Inspection Final Passed 4/21/2023 (8:00 - 10:00) 4/21/2023 (AM) 04/21/2023