PRBD202300171
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed w/ Conditions | 3/8/2023 (8:00 - 10:00) | 3/8/2023 (AM) | 03/08/2023 |
Corrections:
Miscellaneous/Other
Comment Only
03/08/2023
Framing approved for walls, storefront, and soffits. Ok to cover the walls and sides of soffits only.
Bottoms of all soffits to remain open for electrical and sprinkler inspection, once those inspections have taken place and have been approved ... covering the bottoms of soffits will be allowed.
Fireproofing checked and approved.
|
||||
Building Final Inspection | Partial Pass | 4/19/2023 (8:00 - 10:00) | 4/19/2023 (AM) | 04/19/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/19/2023
Approved for bringing in stock and store set up.
Call for the final inspection when storefront has been completed.
|
||||
Fire Inspection Final | Passed | 4/19/2023 (8:00 - 10:00) | 4/19/2023 (AM) | 04/25/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/25/2023
Inspected on 4/19/23, and all was approved per fire inspector Lance S.
Fire inspection was already signed off on the permit card.
|
||||
Building Final Inspection | Passed | 4/25/2023 (8:00 - 10:00) | 4/25/2023 (AM) | 04/25/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/25/2023
Final approved for this scope of work and permit,
.
Fire final was already signed off on the permit card on 4/19/23.
|