PRBD202301069
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Framing Inspection | Passed | 6/14/2023 (7:00 - 8:00) | 6/14/2023 (AM) | 06/14/2023 |
Corrections:
Miscellaneous/Other
Comment Only
06/14/2023
Framing approved.
Note.... contractor is going to add posts in 2 wall sections to get ride of the high bracing above walls. Picture of installed posts to be sent to inspector.
|
||||
Footing Inspection | Passed | 6/21/2023 (7:00 - 8:00) | 6/21/2023 (AM) | 06/21/2023 |
Corrections:
Miscellaneous/Other
Comment Only
06/21/2023
Pad footings with rebar as per plan.... approved
|
||||
Fire Inspection Final | Failed | 9/6/2023 (7:00 - 8:00) | 9/6/2023 (AM) | 09/06/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
09/06/2023
Must hydro sprinkler system, must test fire alarm, must test paint booths, must add and hang fire extinguishers.
|
||||
Progress Inspection | Passed | 09/06/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
09/06/2023
Owners want to set up shelving and unpack tools. Approval tp set up this shop with the necessary tools and equipment needed.
|
||||
Building Final Inspection | Not Ready | 9/6/2023 (7:00 - 8:00) | 9/6/2023 (AM) | 09/06/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/06/2023
Not ready for final inspection, see todays progress inspection.
|
||||
Building Final Inspection | Partial Pass | 9/12/2023 (2:30 - 3:30) | 9/12/2023 (PM) | 09/12/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/12/2023
Approved for a temp occupancy for this project, building may be used for its intended purposes.
There are some inspections pending that need to be set up with the city... lighting/landscape, fire inspection for the new fire panel once installed.
Final for this permit will be given once all required inspections and work is completed.
|
||||
Fire Inspection Final | Issue TCO | 9/12/2023 (2:30 - 3:30) | 9/12/2023 (PM) | 09/15/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
09/15/2023
Must hydro sprinkler system, must test fire alarm, must test paint booths, must add and hang fire extinguishers.
|
||||
Fire Inspection Final | Passed | 10/31/2023 | ||
Corrections:
Miscellaneous/Other
Outstanding
09/15/2023
Must hydro sprinkler system, must test fire alarm, must test paint booths, must add and hang fire extinguishers.
|