Summary

PRBD202301144
Building
Finaled
MSP BLN OFFICE LLC
Alteration/Repair/Replace
Business
Interior renovation of lower level restrooms, locker rooms and workout room.
02/07/2023
02/21/2023
02/27/2024
08/31/2023

Locations

Permits

Permit Number: PRBD202301144

Building
Finaled
02/21/2023
02/27/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 4/6/2023 (8:00 - 10:00) 4/6/2023 (AM) 04/06/2023
Corrections:


Miscellaneous/Other
Comment Only
04/06/2023
Framing of the bathrooms, fitness, and locker rooms.. approved

Framing Inspection Passed 5/25/2023 (10:00 - 12:00) 5/31/2023 (AM) 05/31/2023
Corrections:


Miscellaneous/Other
Comment Only
05/31/2023
Above ceiling approved

Building Final Inspection Partial Pass 8/25/2023 (10:00 - 12:00) 8/25/2023 (AM) 08/25/2023
Corrections:


Miscellaneous/Other
Carried Forward
08/25/2023
1) install accessibility signage to bathrooms. 2) install fire extinguisher in corridor. 3) fire inspection final needed. Reinspection needed for final.

Fire Inspection Final Passed 8/25/2023 (10:00 - 12:00) 8/25/2023 (AM) 08/29/2023
Fire Inspection Final Passed 8/29/2023 (8:00 - 10:00) 8/29/2023 (AM) 08/29/2023
Building Final Inspection Passed 08/31/2023
Corrections:


Miscellaneous/Other
Outstanding
08/25/2023
1) install accessibility signage to bathrooms. 2) install fire extinguisher in corridor. 3) fire inspection final needed. Reinspection needed for final.