PRBD202301276
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Building Final Inspection | Pending | |||
|
Corrections:
Miscellaneous/Other
Outstanding
06/20/2023
Need electrical inspect for final.
Sprinkler permits are stiil in issued status, call for finals on those permits.
|
||||
| Framing Inspection | Passed | 4/4/2023 (8:00 - 10:00) | 4/4/2023 (AM) | 04/04/2023 |
| CUI Lab, main floor ( Former High school library ) ( Demo and remodel ) | ||||
| Above Ceiling Inspection | Passed | 6/16/2023 (8:00 - 10:00) | 6/16/2023 (AM) | 06/16/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/16/2023
Viewed at framing inspection by Brian P.
|
||||
| Fire Inspection Final | Passed | 6/16/2023 (8:00 - 10:00) | 6/16/2023 (AM) | 06/16/2023 |
| Building Final Inspection | Issue TCO | 6/20/2023 (7:00 - 8:00) | 6/20/2023 (AM) | 06/20/2023 |
| Need HVAC final with balance report submitted, Electrical final. | ||||
|
Corrections:
Miscellaneous/Other
Outstanding
06/20/2023
Fire final passed. Need electrical final and HVAC final with balance report submitted to
Jesse Soller@Bloomingtonmn.gov
|
||||
| Building Final Inspection | Passed w/ Conditions | 6/16/2023 (8:00 - 10:00) | 6/16/2023 (AM) | 08/04/2023 |
| All trade inspections must have final inspections . | ||||
|
Corrections:
Miscellaneous/Other
Carried Forward
06/16/2023
Need electrical inspect for final.
Sprinkler permits are stiil in issued status, call for finals on those permits.
|
||||
|
Miscellaneous/Other
Comment Only
06/16/2023
Approved for the contractor to continue setting up space and to complete remaining installations.
See outstanding comments for final inspections.
|
||||