PRBD202301303
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 4/14/2023 (8:00 - 10:00) | 4/14/2023 (AM) | 04/14/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/14/2023
1 hour ceiling framing approved, pending the installation of fasteners at the tracks into wall. Tracks to have fasteners at each stud (16” o.c) and the same where into block wall.
Contractor to verify and take pics for inspection.
|
||||
Progress Inspection | Passed | 10/09/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/09/2023
Contractor performed test of the refrigerant monitoring system to verify the system and show the units ramp up for removal of airfrom the rooms. Contractor and owners want to install equipment in the rooms... approved
|
||||
Framing Inspection | Not Ready | 1/19/2024 (8:00 - 10:00) | 1/19/2024 (AM) | 01/19/2024 |
Corrections:
Miscellaneous/Other
Comment Only
01/19/2024
Not ready for final. Need to confirm locations or rated walls and the area of the scope of work. Mechanical inspection to also be completed for the building final of this permit.
|
||||
Building Final Inspection | Passed | 3/4/2024 (8:00 - 10:00) | 3/4/2024 (AM) | 03/04/2024 |
Corrections:
Miscellaneous/Other
Comment Only
03/04/2024
All completed and walls rated as shown on the plans. Final approved
|
||||
Fire Inspection Final | Passed | 3/4/2024 (8:00 - 10:00) | 3/4/2024 (AM) | 03/05/2024 |