PRBD202301487
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Partial Pass | 03/27/2023 | ||
| Suite 380 : Progress inspection for concrete precast plank fire rated floor penetrations. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
03/27/2023
Progress: suite 380. A. Plug bottom of hole with tight packed foam, drill pin, and fill complete hole with concrete having small aggregate to top of existing floor, and trowel flush to existing concrete floor.
|
||||
|
Miscellaneous/Other
Comment Only
03/27/2023
Foam Plug bottom of hole, and install metal pin, and fill with concrete- mortar mix, flush to existing concrete floor.
|
||||
| Framing Inspection | Partial Pass | 4/4/2023 (8:00 - 10:00) | 4/4/2023 (AM) | 04/04/2023 |
| South side of corridor for all 3rd floor. Awaiting sac approval MN DOT permit, A. Floor penetrations for 3rd floor east tenant and 3rd floor west end for MN DOT. B. Framing for 3rd floor tenants, east and west tenants above. Passed. (Call for above ceiling inspection for 3rd floor hallway corridor) | ||||
| Framing Inspection | Passed | 3/16/2023 (10:00 - 12:00) | 3/16/2023 (AM) | 05/30/2023 |
| Suite 380, fill floor penetrations. Progress inspection. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
03/16/2023
Suite 380. Concrete floor penetrations. 2 hour rated. Fill bottom of penetration with mineral wool, and fill balance of penetration with concrete to top of concrete floor.
|
||||
| Framing Inspection | Passed | 05/30/2023 | ||
| Building Final Inspection | Passed w/ Conditions | 5/30/2023 (12:30 - 2:30) | 5/30/2023 (PM) | 05/30/2023 |
| Suite 330 east end. Financial services. Need all trade finals.(electrical, low voltage, fire sprinkler, mechanical, plumbing. | ||||
| Fire Inspection Final | Passed w/ Conditions | 5/30/2023 (12:30 - 2:30) | 5/30/2023 (PM) | 05/30/2023 |
| Ensure fire extinguisher has an updated inspection tag. | ||||