PRBD202302636
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Above Ceiling Inspection | Failed | 6/14/2023 (8:00 - 10:00) | 6/14/2023 (AM) | 06/14/2023 |
Corrections:
Miscellaneous/Other
Comment Only
06/14/2023
Ceiling framing and above ceiling is not ready for inspection, trades need to finish work above, have inspections, and provide access panels where needed.
Call in for inspection when ready.
|
||||
Framing Inspection | Partial Pass | 6/14/2023 (8:00 - 10:00) | 6/14/2023 (AM) | 06/14/2023 |
Corrections:
Miscellaneous/Other
Comment Only
06/14/2023
Interior Wall framing only approved.
Call in for store front and above ceiling inspections when ready.
|
||||
Above Ceiling Inspection | Passed w/ Conditions | 6/22/2023 (7:00 - 8:00) | 6/22/2023 (AM) | 06/22/2023 |
Corrections:
Miscellaneous/Other
Comment Only
06/22/2023
Above ceiling approved.
Note.... smoke bulkhead to be fastened off for al drywall and penetrations sealed. No covering storefront till inspection has been done for framing, electrical, and sprinkler.
|
||||
Framing Inspection | Passed | 7/6/2023 (10:00 - 12:00) | 06/29/2023 | |
Corrections:
Miscellaneous/Other
Comment Only
06/29/2023
Storefront framing and smoke curtain framing and sealing at gypsum... approved
|
||||
Framing Inspection | Passed | 7/6/2023 (10:00 - 12:00) | 7/6/2023 (AM) | 07/06/2023 |
Corrections:
Miscellaneous/Other
Comment Only
07/06/2023
Framing at storefront coil door... approved
|
||||
Progress Inspection | Passed | 07/18/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/18/2023
Remaining framing at storefront at coiling door location installed and sprinklers set in place... approved.
|
||||
Building Final Inspection | Not Ready | 7/25/2023 (12:30 - 2:30) | 7/25/2023 (PM) | 07/25/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
07/25/2023
Fire proofed columns in storage rooms need to be protected, build gypsum enclosure around columns.
|
||||
Miscellaneous/Other
Comment Only
07/25/2023
Not ready for final or for stocking to take place. Complete work and cleanup, call in for inspection when the bulk of work is completed.
See outstanding comments for correction.
|
||||
Fire Inspection Final | Not Ready | 7/25/2023 (12:30 - 2:30) | 7/25/2023 (PM) | 07/25/2023 |
Building Final Inspection | Partial Pass | 7/27/2023 (8:00 - 10:00) | 7/27/2023 (AM) | 07/27/2023 |
Corrections:
Miscellaneous/Other
Comment Only
07/27/2023
Approved to open to public.
Millwork still on order and needs to be installed. Final for electrical will be pending the installation of lighted cabinets, fire final needed for final of permits.
|
||||
Building Final Inspection | Passed | 9/21/2023 (7:00 - 8:00) | 9/21/2023 (AM) | 09/21/2023 |
Corrections:
Miscellaneous/Other
Resolved
09/21/2023
Fire proofed columns in storage rooms need to be protected, build gypsum enclosure around columns.
|
||||
Miscellaneous/Other
Comment Only
09/21/2023
Final for this permit approved
|
||||
Fire Inspection Final | Passed | 9/21/2023 (7:00 - 8:00) | 9/21/2023 (AM) | 09/22/2023 |