Permit Application Status

PRBD202303003


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202303003
Building
Expired
THE LUTHER COMPANY LLLP
Addition
Business
Storage, moderate hazard
Work involves demolition of the interior front and extending the front half several feet to the north. The addition/alteration also involved expanding the service drive and the shop with the addition of an underground infiltration system. Revised permit on 01/16/23 - no longer doing large addition on south side of building. Will do small addition (480 s.f.) on south side for storage of dumpsters.
03/31/2023
07/21/2023
06/17/2025

Locations

Permits

Permit Number: PRBD202303003

Building
Expired
07/21/2023
06/17/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Building Final Inspection Pending
Housewrap Inspection Pending
Lath Inspection Pending
Insulation Inspection Pending
Footing Inspection Pending
Footing Inspection Not Ready 8/11/2023 (12:30 - 2:30) 8/11/2023 (PM) 08/11/2023
Robert took the afternoon off, and notice was given to me this morning, (same day inspections) by office staff. Robert gave me no e mail notice.
Footing Inspection Not Ready 8/14/2023 (8:00 - 10:00) 8/14/2023 (AM) 08/14/2023
Footing Inspection Passed 8/16/2023 (10:00 - 12:00) 8/16/2023 (AM) 08/16/2023
Corrections:


Miscellaneous/Other
Comment Only
08/16/2023
12“ x 24“ strip footings and pan footings with rebar as per drawings on sandy clay soil approved.

Footing Inspection Passed 8/22/2023 (8:00 - 10:00) 8/22/2023 (AM) 08/22/2023
Corrections:


Miscellaneous/Other
Comment Only
08/22/2023
Foundation wall approved.

Footing Inspection Passed 8/24/2023 (8:00 - 10:00) 8/24/2023 (AM) 08/24/2023
Corrections:


Miscellaneous/Other
Comment Only
08/24/2023
Strip footing and two pad footings on west side of service Drive approved.

Footing Inspection Passed 8/25/2023 (8:00 - 10:00) 8/25/2023 (AM) 08/25/2023
Corrections:


Miscellaneous/Other
Comment Only
08/25/2023
Strip footings at East side of service Drive approved.

Footing Inspection Passed 8/29/2023 (10:00 - 12:00) 8/29/2023 (AM) 08/29/2023
Corrections:


Miscellaneous/Other
Comment Only
08/29/2023
Foundation walls at east side of service Drive approved.

Progress Inspection Passed 10/2/2023 (10:00 - 12:00) 10/2/2023 (AM) 10/02/2023
Corrections:


Miscellaneous/Other
Comment Only
10/02/2023
Progress inspection of structural steel approved.

Framing Inspection Passed 10/9/2023 (10:00 - 12:00) 10/9/2023 (AM) 10/09/2023
Corrections:


Miscellaneous/Other
Comment Only
10/09/2023
Framing of facia/parapet approved. Provide special inspectors summary report of welding when ready.

Progress Inspection Passed 10/11/2023 (12:30 - 2:30) 10/11/2023 (PM) 10/11/2023
Corrections:


Miscellaneous/Other
Comment Only
10/11/2023
Reviewed with contractor on site change of reporting requirements for special inspection reports.

Footing Inspection Passed 8/15/2023 (10:00 - 12:00) 11/17/2023
Moved from 8/15 to Wed 8/16 per Robert's request on 8/14. thanks- vm 8/14/23
Corrections:


Miscellaneous/Other
Comment Only
11/17/2023
Two aprons on west side and one on East side all with rebar as per drawings approved. Vapor barrier under slab throughout service drive approved.

Progress Inspection Passed 11/20/2023 (Morning) 11/20/2023 (AM) 11/20/2023
Corrections:


Miscellaneous/Other
Comment Only
11/20/2023
Progress inspection of framing, OK to cover one side.

Framing Inspection Passed 12/14/2023 (8:00 - 10:00) 12/14/2023 (AM) 12/14/2023
Above Ceiling Inspection Passed 4/5/2024 (8:00 - 10:00) 4/5/2024 (AM) 04/05/2024
Corrections:


Miscellaneous/Other
Comment Only
04/05/2024
Above ceiling and pre-final walk-through approved.

Fire Inspection Final Partial Pass 4/18/2024 (8:00 - 10:00) 4/18/2024 (AM) 04/19/2024
Showroom and office area approved. Fans in customer drop-off bay shall be tied into building fire alarm. Fans shall shutoff upon activation of waterflow alarm.
Progress Inspection Not Ready 4/17/2024 (8:00 - 10:00) 4/17/2024 (AM) 04/19/2024
Progress Inspection Partial Pass 4/19/2024 (AM) 04/19/2024
10 Day Temporary C.O. 4/19 2024 - 4/29 2024
Fire Inspection Final Passed 4/29/2024 (10:00 - 12:00) 4/29/2024 (AM) 04/29/2024
Phase I, customer drop-off to showroom.
Fire Inspection Final Not Ready 4/26/2024 (10:00 - 12:00) 4/26/2024 (AM) 04/30/2024
Same-day cancellation; rescheduling @ Monday 4/29. thx vm 4/26
Footing Inspection Not Ready 7/24/2024 (10:00 - 12:00) 7/24/2024 (AM) 07/24/2024
Cancelled Footing inspection for today, thx. [jsmidt @ 07/24/2024 8:22 AM]
Progress Inspection Partial Pass 7/25/2024 (10:00 - 12:00) 7/25/2024 (AM) 07/25/2024
Corrections:


Miscellaneous/Other
Comment Only
07/25/2024
Partial final approval for parts department only approved.

Footing Inspection Passed 8/1/2024 (10:00 - 12:00) 8/1/2024 (AM) 08/01/2024
Corrections:


Miscellaneous/Other
Comment Only
08/01/2024
24“ x 12“ strip footing with two number five rebar as per plan on mixed soil types approved.

Framing Inspection Partial Pass 9/24/2024 (8:00 - 10:00) 9/24/2024 (AM) 09/24/2024
Framing for interior. PASSED. ( PARTIAL PASS FOR ONGOING INSPECTIONS.)
Framing Inspection Passed 10/3/2024 (8:00 - 10:00) 10/3/2024 (AM) 10/03/2024
Corrections:


Miscellaneous/Other
Comment Only
10/03/2024
Partial framing inspection to include locker room, parts and partial roof framing at South end all approved contingent on electrical rough approval.

Landscaping Inspection Failed 10/9/2024 10/09/2024
Luther
Landscaping Inspection Passed 11/4/2024 11/8/2024 11/04/2024
Progress Inspection Passed 11/21/2024 (10:00 - 12:00) 11/21/2024 (AM) 11/21/2024
Corrections:


Miscellaneous/Other
Comment Only
11/21/2024
Partial final approval for break room and two restrooms only, approved.

Lighting Inspection Passed 5/31/2025 12/19/2024
Hyundai Luther Company