PRBD202304681
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Passed | 7/5/2023 | 7/5/2023 (AM) | 07/05/2023 |
Corrections:
Miscellaneous/Other
Comment Only
07/05/2023
Slab replacement with rebar approved.
|
||||
Progress Inspection | Passed | 7/7/2023 (8:00 - 10:00) | 7/7/2023 (AM) | 07/07/2023 |
Corrections:
Miscellaneous/Other
Comment Only
07/07/2023
Framing approved contingent on electrical and plumbing rough in approvals.
|
||||
Fire Inspection Final | Issue TCO | 8/4/2023 (8:00 - 10:00) | 8/4/2023 (AM) | 08/04/2023 |
Add 2 emergency lights and 1 exit sign towards the back. | ||||
Building Final Inspection | Issue TCO | 8/4/2023 (8:00 - 10:00) | 8/4/2023 (AM) | 08/04/2023 |
Corrections:
Miscellaneous/Other
Carried Forward
08/04/2023
1. Add to exit signs as discussed in field. 2. Provide signage and drain covers in new toilet rooms. 3. Need final fire approval. 4. 30 day temporary CO approved for stocking and employee use only.
|
||||
Fire Inspection Final | Passed | 8/17/2023 (10:00 - 12:00) | 8/17/2023 (AM) | 08/17/2023 |
Building Final Inspection | Passed | 8/17/2023 (10:00 - 12:00) | 8/17/2023 (AM) | 08/18/2023 |
Corrections:
Miscellaneous/Other
Outstanding
08/04/2023
1. Add to exit signs as discussed in field. 2. Provide signage and drain covers in new toilet rooms. 3. Need final fire approval. 4. 30 day temporary CO approved for stocking and employee use only.
|
||||
Framing Inspection | Passed | 08/18/2023 | ||
Passed framing under Progress inspection on 7/7/2023. |