PRBD202305454
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 12/20/2023 (10:00 - 12:00) | 12/20/2023 (AM) | 12/20/2023 |
Corrections:
Miscellaneous/Other
Comment Only
12/20/2023
Wall Framing approved.
|
||||
Progress Inspection | Partial Pass | 02/01/2024 | ||
Corrections:
Miscellaneous/Other
Comment Only
02/01/2024
Viewed the shafts insde janitor closets of each floor from 7th to roof where core board was reinstalled from the ducting installation to 7th floor to roof. Core board installation approved.
Contractor to provide pictures to inspector of each floor level repair to shaft of each layer along with the modifications that were discussed at time of inspection for compliance to the shaft wall assembly.
|
||||
Building Final Inspection | Failed | 2/1/2024 (10:00 - 12:00) | 2/1/2024 (AM) | 02/01/2024 |
Corrections:
Miscellaneous/Other
Comment Only
02/01/2024
Not ready, see today's progress inspection.
|
||||
Fire Inspection Final | Not Ready | 2/1/2024 (10:00 - 12:00) | 2/1/2024 (AM) | 02/01/2024 |
Fire Inspection Final | Passed | 02/06/2024 | ||
Building Final Inspection | Partial Pass | 2/7/2024 (8:00 - 10:00) | 2/7/2024 (AM) | 02/07/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
02/07/2024
RTU to be installed when it comes in from delivery, dampers to be tested when unit is installed.
This buildout is completed other than the roof top unit. The city will allow a Temp / partial final for this permit pending the unit and damper's inspection and testing.
|
||||
Miscellaneous/Other
Comment Only
02/07/2024
The shafts are completed for closure-to maintain rating... approved.
See outstanding comments for final of this permit. Temp approved at this time.
|
||||
Building Final Inspection | Passed | 5/3/2024 (8:00 - 10:00) | 5/3/2024 (AM) | 05/03/2024 |
Corrections:
Miscellaneous/Other
Resolved
05/03/2024
RTU to be installed when it comes in from delivery, dampers to be tested when unit is installed.
This buildout is completed other than the roof top unit. The city will allow a Temp / partial final for this permit pending the unit and damper's inspection and testing.
|
||||
Miscellaneous/Other
Comment Only
05/03/2024
All permits and inspections are completed, final for this permit approved.
|