Permit Application Status

PRBD202305454


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202305454
Building
Finaled
NORTH PAD DEVELOPMENT LLC
Alteration/Repair/Replace
Business
Tenant interior improvements at 7th floor of MOA Office Tower
05/24/2023
11/20/2023
10/30/2024

Locations

Permits

Permit Number: PRBD202305454

Building
Finaled
11/20/2023
10/30/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 12/20/2023 (10:00 - 12:00) 12/20/2023 (AM) 12/20/2023
Corrections:


Miscellaneous/Other
Comment Only
12/20/2023
Wall Framing approved.

Progress Inspection Partial Pass 02/01/2024
Corrections:


Miscellaneous/Other
Comment Only
02/01/2024
Viewed the shafts insde janitor closets of each floor from 7th to roof where core board was reinstalled from the ducting installation to 7th floor to roof. Core board installation approved. Contractor to provide pictures to inspector of each floor level repair to shaft of each layer along with the modifications that were discussed at time of inspection for compliance to the shaft wall assembly.

Building Final Inspection Failed 2/1/2024 (10:00 - 12:00) 2/1/2024 (AM) 02/01/2024
Corrections:


Miscellaneous/Other
Comment Only
02/01/2024
Not ready, see today's progress inspection.

Fire Inspection Final Not Ready 2/1/2024 (10:00 - 12:00) 2/1/2024 (AM) 02/01/2024
Fire Inspection Final Passed 02/06/2024
Building Final Inspection Partial Pass 2/7/2024 (8:00 - 10:00) 2/7/2024 (AM) 02/07/2024
Corrections:


Miscellaneous/Other
Carried Forward
02/07/2024
RTU to be installed when it comes in from delivery, dampers to be tested when unit is installed. This buildout is completed other than the roof top unit. The city will allow a Temp / partial final for this permit pending the unit and damper's inspection and testing.

Miscellaneous/Other
Comment Only
02/07/2024
The shafts are completed for closure-to maintain rating... approved. See outstanding comments for final of this permit. Temp approved at this time.

Building Final Inspection Passed 5/3/2024 (8:00 - 10:00) 5/3/2024 (AM) 05/03/2024
Corrections:


Miscellaneous/Other
Resolved
05/03/2024
RTU to be installed when it comes in from delivery, dampers to be tested when unit is installed. This buildout is completed other than the roof top unit. The city will allow a Temp / partial final for this permit pending the unit and damper's inspection and testing.

Miscellaneous/Other
Comment Only
05/03/2024
All permits and inspections are completed, final for this permit approved.